成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼
2010年PMP美国项目管理考试习题及答案七十五
QUEST Which of the following is based on an individual identification with a more powerful person.
A expert power
B reward power
C referent power
D A and B.
E A and C
参考答案:C
QUEST Which of the following results are Win/Win conflict resolution?
A compromising
B forcing
C problem solving
D smoothly
E withdraw
参考答案:C
QUEST Which of the following organizations has the best technical project control?
A matrix
B functional
C projectized
D B and C
E A and B
参考答案:D
QUEST The functional organization is effective with a mature product or single product line.
A TRUE
B FALSE
C参考答案:
D参考答案:
E参考答案:
参考答案:A

QUEST The strong matrix versus a weak matrix.
A team members are more likely to be assigned to the project office in a strong matrix
B strong matrix is more difficult to manage.
C the balance of power has shifted away from the PM.
D functional managers no longer has control over the technical processes.
E All of the above.
参考答案:A
相关试题:
2010年PMP美国项目管理考试习题及答案七十四
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3

