成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼
2010年PMP美国项目管理考试习题及答案六十二
QUEST At least _____of the cost of quality are the direct responsibility of management.
A 25%
B 85%
C 50%
D 100%
E 33%
参考答案:B
QUEST Non-conformance penalties are a form of _____.
A quality incentive
B risk sharing
C contract negotiations
D quality assurance programs
E None of the above.
参考答案:C
QUEST Quality Improvement Programs are normally associated with which two of the following?
A Juran and Crosby
B Juran and Deming
C Crosby and Deming
D Deming and the Japanese
E Crosby and the Japanese
参考答案:D
QUEST The initial cost of a product and the product's operation and maintenance costs _____ .
A increases perceived value when balanced.
B are incidental to each other because initial costs are "sunk"
C decreases design costs as operation periods increase
D provides perceived function value and product social dysfunction
E are integrally related with each other because initial costs are "sunk".
参考答案:A

QUEST Quality control is normally performed by the _____ .
A QA personnel
B project team
C operating personnel
D project management
E None of the above.
参考答案:C
相关试题:
2010年PMP美国项目管理考试习题及答案六十一
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3
本文内容来自自互联网公开信息或用户自发贡献,该文观点仅代表作者本人,版权归原作者所有。本站仅提供信息存储空间服务,不拥有所有权,不承担相关法律责任。若发现侵权或违规内容请联系电话4008352114或邮箱442699841@qq.com,核实后本网站将在24小时内删除侵权内容。

