2010年PMP美国项目管理考试习题及答案六十二
QUEST At least _____of the cost of quality are the direct responsibility of management.
A 25%
B 85%
C 50%
D 100%
E 33%
参考答案:B
QUEST Non-conformance penalties are a form of _____.
A quality incentive
B risk sharing
C contract negotiations
D quality assurance programs
E None of the above.
参考答案:C
QUEST Quality Improvement Programs are normally associated with which two of the following?
A Juran and Crosby
B Juran and Deming
C Crosby and Deming
D Deming and the Japanese
E Crosby and the Japanese
参考答案:D
QUEST The initial cost of a product and the product's operation and maintenance costs _____ .
A increases perceived value when balanced.
B are incidental to each other because initial costs are "sunk"
C decreases design costs as operation periods increase
D provides perceived function value and product social dysfunction
E are integrally related with each other because initial costs are "sunk".
参考答案:A

QUEST Quality control is normally performed by the _____ .
A QA personnel
B project team
C operating personnel
D project management
E None of the above.
参考答案:C