2010年PMP美国项目管理考试习题及答案八十
QUEST Listening involves more than hearing sounds. The good listener
A Repeats some of the things said
B Finishes the speaker's sentences
C Writes everything down
D Nods his head frequently
E参考答案:
参考答案:A
QUEST In general, the best long-lasting approach to settling project conflict is the _____ approach .
A Problem solving
B Compromise
C Withdrawal
D Smoothing
E Forcing
参考答案:A
QUEST The positive value of conflict is underestimated. Properly managed, conflict is a valuable tool, particularly when
A A diversion is needed
B Conflictive situations are in their early stages and emotional involvement is low
C Conflictive situations are in their late stages and emotional involvement is high
D Conflict may cause a loss of status or position power
E参考答案:
参考答案:B
QUEST There are hard causes of conflict (e.g. conflicting schedules) and soft causes. Soft causes are as important as hard causes. Soft causes include diversity of disciplinary expertise, _____, and the project manager's power of reward and punishment.
A Performance tradeoffs
B Ambiguity of roles
C Administrative procedures
D Determining earned value
E参考答案:
参考答案:B

QUEST When planning, organizing, coordinating, and controlling a project an important human resources skill or ability would be
A Building multi-disciplinary teams
B Managing conflict
C Communicating orally and in writing with all levels of personnel
D Involving senior management
E All are important
参考答案:E