QUEST The best way to insure quality conformance is to _____.
A distribute the responsibility to subordinates.
B maintain total control.
C train each worker to implement the work.
D inspect quality into the project.
E None of the above.
参考答案:C
QUEST In order to achieve long-term quality improvements, management must do the following:
A Motivate the employees with seminars, contests, and institute programs such as "Quality Improvement' day.
B Create a quality control department and give the head of the department ultimate responsibility for quality improvement.
C Implement of a formal quality control program with worker and management involvement.
D Establish financial incentive packages for worker.
E A and D
参考答案:C
QUEST The zero defects concept
A is a performance standard for management
B is a motivational technique that promotes "doing it right the first time".
C is used by management to communicate to all employees that everyone should do things right the first time.
D A and C.
E B and C
参考答案:D
QUEST An acceptance control chart has limits that are based on the spec. limits for the product rather than limits which differentiate between random and assignable causes. Under which of the following circumstances should a QC manager consider this type chart
A When the engineering tolerance on a dimension greatly exceeds the natural dispersion of the manufacturing process
B When the number of samples outside the current control chart limits become too costly and cumbersome to investigate.
C When a process is subject to constant but stable tool wear.
D A and B.
E A and C
参考答案:E

QUEST In the project environment, the individual ultimately responsible for quality control is:
A The line workers who must strive "to do things right the first time" to avoid quality problems.
B the company's quality control manager who must work with the project members to ensure the quality control program is effective.
C The head of the production department who retains ultimate quality control responsibility for all the company's projects.
D The project manager who has ultimate responsibility for the entire project.
E the customer who must ensure that he is receiving a quality product from the vendor.
参考答案:D
相关试题:
2010年PMP美国项目管理考试习题及答案六十三
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3
本文内容来自自互联网公开信息或用户自发贡献,该文观点仅代表作者本人,版权归原作者所有。本站仅提供信息存储空间服务,不拥有所有权,不承担相关法律责任。若发现侵权或违规内容请联系电话4008352114或邮箱442699841@qq.com,核实后本网站将在24小时内删除侵权内容。