QUEST Ouchi's Theory Z relates more to _____ whereas Theory X / Theory Y relates to _____ .
A Project managers; team members
B Company management philosophy in treating employees; the average worker
C Project sponsors; project managers
D The functional team; project sponsors
E Recruitment policy; wage and salary administration
参考答案:B
QUEST In which organizational form do project managers usually get to know the employees well enough to provide an input into their performance review?
A Expediter
B Coordinator
C Pure project
D Matrix
E Line-staff
参考答案:C
QUEST In a matrix organizational form, MBO may be difficult to implement:
A If the functional employees are supervised closely by the line manager rather than the project manager
B Unless the project manager has an input into the employee's performance review
C Unless the project and line managers agree on the ultimate objective
D Unless the project and line managers agree to the duration of the task
E None of the above are correct answers
参考答案:E
QUEST Perhaps the biggest problem facing the project manager during integration activities within a matrix structure is:
A Coping with employees who report to multiple bosses
B Too much sponsorship involvement
C Unclear functional understanding of the technical requirements
D Escalating project costs
E All of the above
参考答案:A

QUEST The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form does the project manager probably have the easiest time in integrating work?
A Matrix
B Classical
C Expediter
D Coordinator
E Pure project
参考答案:E
相关试题:
2010年PMP美国项目管理考试习题及答案八十二
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3
本文内容来自自互联网公开信息或用户自发贡献,该文观点仅代表作者本人,版权归原作者所有。本站仅提供信息存储空间服务,不拥有所有权,不承担相关法律责任。若发现侵权或违规内容请联系电话4008352114或邮箱442699841@qq.com,核实后本网站将在24小时内删除侵权内容。