QUEST A team that is just forming needs:
A An organization chart
B Alternatives and choices
C Structure and specificity
D Orientation and organization
E Opportunities for dialogue and conflict resolution
参考答案:C
QUEST The capacity to get an individual or group to perform a given task is described as:
A Authority
B Power
C Influence
D Leadership
E Motivation
参考答案:E
QUEST A project manager believes that the best way to manage is to form a good, harmonious working relationship with the team, and high performance will follow. The project manager could be defined as a _____ manager.
A 1,9
B 9,1
C 1,1
D 9,9
E 5,5
参考答案:A
QUEST Project leadership requires that the project manager pay attention simultaneously to the:
A Tasks to be performed and needs of the team
B Quantity and quality of the work to be performed
C Efficiency and effectiveness of the team
D Time, cost and performance deliverables
E All of the above
参考答案:E

QUEST Which of the following can the project manager use as a means of measuring project team effectiveness?
A Absenteeism
B Sponsor-approved salary increases
C Efficiency of the team
D Turnover of personnel
E Grievances
参考答案:C