PMP认证考试练习题及参考答案(二十二)
1. project life cycles provide a better means of measurement of progress and control. the four phases of a project are conceptual development,
_____, _____, and _____.
a. preliminary planning, detail planning, closeout
b. implementation, reporting, termination
c. development, implementation, termination
d. execution, reporting, finishing
e. implementation, termination, post-audit review
ans: c
2. response planning is the responsibility of the functional areas and considers
a. mitigation.
b. deflection.
c. contingency planning.
d. unforeseen occurrences.
e. all of the above.
ans: ehttp://ks.examda.com
3. the definitive terms of a contract are written during which of the following contract phases?
a. contract phase
b. post-award phase
c. award phase
d. pre-award phase
e. requirement phase
ans: c
4. the sending or conveying of information from one place to another is the process of
a. networking
b. transmitting
c. interacting
d. promoting
e. interfacing
ans: b
5. which of the following types of cost are relevant to making financial decisions:
a. sunk cost
b. opportunity cost
c. material cost
d. a and c onlywww.Examda.CoM
e. b and c only
ans: e
6. in preparing a good project definition, experienced project managers will:
a. concentrate mainly on the end product rather than costs or benefits. these come later.
b. realize that only the "tip of the iceberg" may be showing. as a project manager, you must get beneath it.
c. understand that a project definition/plan is a dynamic rather than static tool, and thus subject to change.
d. try to convert objectives into quantifiable terms.
e. all of the above
ans: e
7. in which of the following is the cost of risk hidden by the contractor?
a. firm fixed price contract
b. fixed price plus incentive
c. cost plus fixed price
d. cost plus percentage of cost
e. a and b
ans: d来源:考试大网
8. management of a certain building was receiving complaints about slow elevator service. the solution adopted was to add mirrors in the
lobbies to reduce boredom while passengers waited. this is an example of _____ .
a. kepner-tregoe method
b. potential problem analysis
c. decision analysis
d. creative problem solving
e. none of the above
ans: d
9. pure risk differs from business risks because pure risk's _____ .
a. include chances of both profit or loss associated with the business.
b. include chances of loss and no chances for profit associated with the business.
c. must incur personal loss with business liability.
d. must incur business liability associated with loss of pure profit.
e. b and c
ans: b来源:考试大
10. the actual configuration of a pert/cpm network _____ the amount of resources that can be devoted to the project.
a. increases.
b. is not affected by
c. does not require
d. is heavily dependent upon
e. is the only means of determining
ans: d
11. the following types of costs are relevant to making a financial decision except:
a. opportunity costs
b. direct costs
c. sunk cost
d. unavoidable costs
e. none of the above
ans: c
12. the standard types of communication include all but
a. written
b. verbal
c. telepathic
d. nonverbal
e. none of the above
ans: c
13. _____ of the extra costs of the project can often be attributed to a lack of quality.
a. 0.12
b. 0.15
c. 0.2
d. 0.25
e. less than 10%
ans: c
14. a budget estimate should give the manager cost data accurate to within:
a. -5 to +10 percent of actual cost
b. -25 to +75 percent of actual cost
c. -30 to +75 percent of actual cost
d. -10 to +25 percent of actual cost考试大论坛
e. none of the above
ans: d
相关练习题:
PMP认证考试最新练习题及参考答案汇总
精品推荐:
PMP全真试题精选
欢迎进入在线试听:项目管理网上辅导,热招中!!
更多信息请进入:项目管理海量题库 考试大项目管理论坛
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1安全工程师辅导资料:电力生产员工心理危险点的预控
- 2浙江临海深入推进村庄整治
- 3招标师学习资料:政府采购范围、管理
- 42015年安全工程师生产管理知识模拟精选(9)
- 52015年安全工程师考试《事故案例分析》试题(9)
- 6云南发力能源奠定高端装备制造基础
- 7工程造价基础知识:标底的编制原则
- 8按成因分类的地震类型
- 9投标过程中的保密管理 主要内容
- 102008年监理工程师《质量、投资、进度控制》习题26
- 11江苏首个模块建筑在镇江开工 房子抗震达8.5级
- 122015年咨询工程师《宏观经济政策与发展规划》每日一练11.14
- 132015年造价工程师考试(土建)知识点精选(11)
- 142015年监理工程师考试考前心情平复法
- 15全国二级注册消防工程师报名时间
- 16地下室底板聚乙烯丙纶防水卷材防潮层施工方法
- 17[重庆]市政工程地下停车场隧道施工组织设计(投标 2012)
- 18建设方工程进度计划
- 192015造价工程师《理论与法规》专家辅导(14)
- 20安全工程师答疑精华:解除合同
- 21安全工程师考试《安全生产管理》第三讲讲义精选(35)
- 222015年咨询工程师《工程咨询概论》每日一练(4.16)
- 23混凝土泵安全操作规程
- 24五星级酒店室内精装饰工程施工组织设计117p
- 25安全工程师生产法复习资料——资质注销
- 26国内PMP的通过率有多高
- 272015年咨询工程师《咨询概论》模拟试题(二)
- 282015年枣庄安全工程师考试报名时间为6月1日-17日
- 292015年招标师《专业实务》辅导:招标师中的招标主体范围
- 30造价工程师建设工程计价复习资料——设备、材料采购的综合评标价法
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼