PMP认证考试练习题及参考答案(十五)
1. things that distort, distract, or muddle the communication process are called:
a. noise
b. selective filtering
c. selective perception
d. medium problems
e. all of the above.http://ks.examda.com
ans: a
2. which is not a consideration in a make or buy decision?
a. cost factors (least cost alternatives)
b. competitors' method of sourcing
c. existence of sufficient administration/technical personnel
d. political and social factors
e. none of the above.
ans: b
3. a work breakdown structure:
a. assures all work is identified
b. subdivides the project into manageable segments
c. provides the project sponsor with a time-phase task summary
d. both a and b
e. all of the above.来源:考试大
ans: d
4. a project manager can exchange information with the project team using which media?
a. tactile
b. audio
c. olfactory
d. visual
e. all of the above.
ans: e
5. during project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. the baseline
schedule:
a. now becomes the new schedule, including the changes, and the original baseline is disregarded.
b. is still the original baseline but annotated to reflect that a change has taken place.
c. is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
d. is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
e. is the same since baseline schedules cannot change once the development phase is completed.
ans: c
6. sensitivity analysis can be used in risk analysis to:
a. substitute for uncertainty analysis in risk quantification
b. estimate the level of risk aversion adopted by management
c. estimate the effect of change of one project variable on the overall project
d. a and b
e. all of the above.来源:www.examda.com
ans: c
7. the pareto principle is a technique used by quality managers to determine which quality control problems of a particular service or
manufacturing process should be corrected. which of the following statements represents the philosophy of the principle?
a. in order to minimize financial losses from quality control problems, all problems which have a measurable cost associated with them should be
corrected.
b. the majority of defects are caused by a small percentage of the identifiable problems. improvements efforts should be reserved for these vital
few problems.
c. in order to achieve zero defects, all quality control problems, including those which do not have a direct financial cost should be corrected.
d. generally, 80 % of the quality control problems are justifiable for correction via cost-benefit analysis. the remaining 20% are not financially
worthy of improvement efforts.
e. a and d
ans: b
8. the budgeted cost of the work performed (bcwp) for a task that has just been completed can be calculated by:
a. multiplying the actual hours worked on the project by the budgeted labor rate.
b. multiplying the budgeted hours to complete the task by the budgeted labor rate.
c. dividing the actual hours required to complete the task by the budgeted labor rate.
d. cannot be determined.
e. none of the above来源:考试大
ans: b
9. the project manager has, as a prime responsibility, to assure proper integration of activities. in which organizational form does the project
manager probably have the easiest time in integrating work?
a. matrix
b. classical
c. expediter
d. coordinator
e. pure project
ans: e
10. there are four methods of government procurement. which is not one of these methods?
a. assistance
b. sealed bidding
c. competitive proposals
d. acquisition考试大(www.Examda。com)
e. small purchases
ans: d
11. a scientist is informing techs. about a new product which is starting and the type of work that the lab techs. will be expected to do. the
barriers which could hinder the lab techs. ability to filter the information include all of the following except:
a. language and semantics
b. culture and ethics
c. intelligence and knowledge base
d. reputation, authority, organizational status and position
e. relative location of the lab to the scientist's office
ans: e
12. many companies self insure against some risk. problems which can arise from self-insurance include:
a. failure to reserve funds to handle worst case scenarios (low probability events) resulting in severe financial damage to the company
b. stiff competition from insurance companies
c. confusion of business risks with insurable risks.
d. a and c
e. all of the above.
ans: d
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1机械车载式混凝土输送泵主要技术参数:
- 2钢结构施工流程中易出现的问题
- 3安全工程师生产技术复习要点:运输线防护问题
- 4上承式钢管混凝土拱桥盖梁预制吊装施工工法
- 5清淤换填试验段施工方法
- 62015年二级建造师《法规及相关知识》每日一练(2.20)
- 72015年招标师考前经典试题分享(18)
- 8《招标采购法律法规与政策》第二章:中央投资项目招标
- 92015年咨询工程师《工程咨询概论》每日一练3.31
- 102015年招标师《招标采购案例分析》串讲讲义下载(5)
- 11槽底淤积物对墙体质量影响
- 122015年二级建造师《建筑》重点:混凝土结构耐久性设计
- 13地铁与轻轨的区别
- 14安全生产事故案例分析:案例15及练习
- 15任宏军:加强我国核电闭式核燃料循环体系研发
- 16搭设和拆除作业中的安全防护
- 17国土资源部:严控城市新区无序扩张 防"摊大饼"现象
- 18【招标师考试】项目管理与招标采购第三章:行情调研
- 19咨询工程师《工程项目组织与管理》练习习题(4)
- 20[四川]06年造价工程师考试报考总人数为3930人
- 21造价工程师技术与计量复习要点:结算工程
- 222015年咨询工程师《工程项目组织与管理》每日一练(8.13)
- 23造价工程师建设工程造价管理复习资料——造价工程师的权利
- 24求能够进行变更管理以及版本管理的项目管理工具?
- 25政府采购法 第四章 政府采购程序
- 262015年咨询工程师《现代咨询方法与实务》练习题(47)
- 27鍒╃敤椋庣Н娌欏~绛戦珮绛夌骇鍏?矾璺?熀鏂藉伐宸ユ硶
- 28[辽宁]钢骨混凝土柱施工技术
- 29如何应对质疑与投诉
- 30[青海]06年注册安全师考试网上成绩查询
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼