PMP认证考试练习题及参考答案(三十)
A 21
B 22
C 23
D 24
E 25
ans:D
2 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?
A P
B Q
C R
D S
E T
ans:A
3 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
A 0
B 1
C 2
D 3
E 4
ans:D
4 Using the figure in the Special window, The critical path is:
A A-B-G
B C-G
C C-D
D E-F
E A-B-G and C-D
ans:B
5 The first step in building a PERT/CPM network is to:
A Create a flow chart
B Determine the critical path
C Show task relationships
D Create a work breakdown structure
E None of the above.
ans:D
6 The critical path in a schedule network is the path that:
A Takes the longest time to complete
B Must be done before any other tasks
C Allows some flexibility in scheduling a start time.
D Is not affected by schedule slippage
E All of the above.
ans:A
7 Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:
A The project's schedule will be reduced by 2 weeks.
B The available slack on the noncritical paths will increase.
C A new critical path may appear after the crash.
D All of the above.
E A and B only.
ans:C
8 Your team has prepared a CPM schedule for your review. You notice that one node has six inputs (including two dummy activities) and four outputs (which include one dummy activity). Select the correct statement from the following:
A This is a valid representation if the logic is correct.
B This is invalid because a node can have a maximum of one dummy input representation if the logic is correct.
C This is invalid because nodes cannot have both dummy inputs and dummy outputs.
D This is a invalid because the number of outputs must equal the number of inputs.
E This is invalid because a maximum of two inputs and two outputs are allowed using the critical path method.
ans:A
9 During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:
A Now becomes the new schedule, including the changes, and the original baseline is disregarded.
B Is still the original baseline but annotated to reflect that a change has taken place.
C Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
D Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
E Is the same since baseline schedules cannot change once the development phase is completed.
ans:C
10 Network schedules are prepared during the _____ phase and updated during the _____ phase.
A Conceptual, execution.
B Development, implementation.
C Development, close-out.
D Implementation, close-out.
E Planning, finishing.
ans:B
11 Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:
A The project manager and project office personnel.
B The project team and functional managers.
C The project sponsor.
D All of the above.
E A and B only.
ans:E
12 Increasing resources on the critical path activities may not always shorten the length of the project because:
A Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).
B Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.
C The skill level of the added resources might not be appropriate for the activities to be performed.
D Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)
E All of the above.
ans:E
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1橡皮土怎么处理?
- 2全站仪后方交会在中小型矿井定向中的应用探讨
- 32015年咨询工程师《工程项目组织与管理》每日一练(11.14)
- 42015年监理工程师《三控》选择第11-20题
- 5二级建造师法规知识点:投标文件的修改与撤回
- 6工业厂房工程施工进度计划横道图(自动计算)
- 7四车道高速公路特长隧道施工组织设计(133页)
- 8公路桥工程水泥混凝土方形灌注桩施工工法(中交)
- 9中粮成都铁路专线竣工
- 10浅谈煤矿井下火灾的抢救处理
- 11工程造价基础知识建设工程招标:建设工程招标的范围
- 12某综合楼水暖电安装工程施工组织设计 39p
- 132015年招标师考试招标采购专业实务考前复习指导(80)
- 142015年招标师《专业实务》辅导:招标阶段
- 152015年咨询工程师考试练习题《工程咨询概论》(7)
- 16框架剪力墙结构适用范围
- 17园林绿化景观工程施工组织设计99p
- 18[内蒙古]06年造价工程师考试6.8-11日网上补报名
- 192015年造价工程师考试辅导:招标投标法
- 202015年二级建造师《法规》重点:注册建造师傅当履行的义务
- 21市政公用工程施工项目目标成本分析的内容
- 22安全工程师《安全生产管理》第三讲讲义精选(12)
- 23名师达江解答二级建造师相关疑问——报名篇(五)
- 24一级建造师管理与实务复习要点:标书审查
- 25一级建造师管理与实务复习要点:路基的合格标准
- 262015年咨询工程师《工程项目组织与管理》每日一练2.27
- 272012年pmp模拟试题及答案(八)
- 282015年福建造价工程师考试报名时间为6月28日-7月24日
- 29安全工程师《生产法及相关法律知识》预测试题(8)
- 30注册咨询工程师2015年《项目决策分析》习题(4)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼