PMP认证考试练习题及参考答案(二十五)
A A grouping of related activities which last two years or more
B The first major subdivision of a project
C A grouping of projects, similar in nature, which support a product or product line and have no definable end point
D A product line 来源:www.examda.com
E Another name for a project
ans:C
2 Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:
A The project manager
B The functional manager
C The project sponsor
D The client
E All of the above
ans:A
3 The project charter is a document designed to tell _____ exactly what the project entails.
A The project manager
B The project office
C The project team
D The project sponsor
E Anyone associated with the project
ans:E
4 Work authorization forms are needed in order to:
A Authorize line organizations to charge against the project
B Establish an audit trail
C Develop a structured methodology for release of funds
D All of the above 来源:考试大网
E A and C only
ans:D
5 The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
ans:E
6 Typical characteristics of a work package include:
A Representation of units of work at a level where work is performed
B Clearly distinguishes one work package from all others assigned to a single functional group
C Limits the work to be performed to relatively short periods of time
D All of the above
E A and B only
ans:E
7 Problems can occur in properly defining a project because:
A Project goals may not be agreeable to all parties
B The plan was "too loose," thus allowing priorities to change
C Low turnover of project personnel
D Too much communication between the client and project personnel
E The project objectives were quantified
ans:A
8 In preparing a good project definition, experienced project managers will:
A Concentrate mainly on the end product rather than costs or benefits. These come later.
B Realize that only the "tip of the iceberg" may be showing. As a project manager, you must get beneath it.
C Understand that a project definition/plan is a dynamic rather than static tool, and thus subject to change.
D Try to convert objectives into quantifiable terms.
E All of the above 考试大(www.Examda。com)
ans:E
9 Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
A Preliminary planning, detail planning, closeout
B Implementation, reporting, termination
C Development, implementation, termination
D Execution, reporting, finishing
E Implementation, termination, post-audit review
ans:C
10 The contractual statement of work (CSOW)
A Must be the same as the proposal statement of work
B Does not identify reporting requirements
C Can be at a different level of detail (i.e. WBS level) than the proposal statement of work
D Identifies the contractor's organizational structure for the project
E All of the above
ans:C
11 Which of the following can result in misinterpretation of the statement of work?
A Using imprecise language (i.e. nearly, approximately)
B Mixing tasks, specifications, special instructions and approvals
C No pattern, structure or chronological order
D Wide variation in the size of tasks or details of work
E All of the above
ans:E
12 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
A Change the scope baseline
B Prepare a variance report
C Call a meeting of the configuration control board
D Change the project's objectives
E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
ans:E
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1二建复习资料模板安全技术
- 2浙江造价工程师2013年考试7月10日开始报名
- 3项目决策分析与评价知识点:场(厂)址比选
- 4机械张拉预应力筋时,张拉控制应力值为什么先张法高于后张法
- 5一级建造师管理与实务复习要点:拱架受力反弯点
- 6现浇预应力清水混凝土单箱五室鱼腹式简支梁施工工法
- 7一级建造师《机电工程》自动化仪表工程安装技术(1)
- 82015年咨询工程师《工程咨询概论》每日一练(2.6)
- 92015年咨询工程师《项目决策分析与评价》每日一练(1.2)
- 102015年造价工程师考试辅导资料:火焰切割
- 11高边坡脚手架拆除卸运最新施工工艺
- 12软件项目管理系统中安全监管的主要对策
- 13种植屋面施工工艺标准521
- 14安全工程师案例分析复习要点:伤亡事故标准
- 15某地铁车站主体结构防水工程施工方案
- 162015年咨询工程师知识点:SWOT分析
- 172015年二级建造师报名骗局
- 18《工程项目组织与管理》知识点:组织计划实施
- 19搅拌车打蜡要注意事项
- 20某工程屋面防水施工方案(氯化聚乙烯防水卷材)
- 21招标师法律法规:招标的方式
- 222015年造价员基础知识:资产的分类
- 232015年招标师考试招标采购法律法规与政策辅导讲义二十
- 24土钉与锚杆有哪些主要区别?
- 25钢筋混凝土结构的设计要求
- 262015造价员《土建工程》知识:地基处理
- 272013年二级建造师《施工管理》每日一练(12.31)
- 28招标师职业水平考试:项目管理与招标采购第一章练习题3
- 29招标投标常见的争议及其表达方式
- 30甘肃实施21.3万户农村危旧房改造
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼