PMP认证考试练习题及参考答案(十六)
1. fixed-price and incentive-type contracts place responsibility for performance and financial risks associated with delay or non-performance on
the:
a. buyer
b. third party
c. contractor
d. all of the above
e. none of the above
ans: c来源:考试大
2. in a contract, the point of total assumption refers to the point where:
a. the customer incurs the total financial responsibility for each additional dollar spent.
b. the contractor incurs the total financial responsiblity for each dollar spent.
c. the schedule and cost variance are zero.
d. the customer will incur no further costs for the work the contractor performs in the completion of the contract.
e. b and d only.
ans: e
3. in a matrix organizational form, mbo may be difficult to implement:
a. if the functional employees are supervised closely by the line manager rather than the project manager
b. unless the project manager has an input into the employee's performance review
c. unless the project and line managers agree on the ultimate objective
d. unless the project and line managers agree to the duration of the task
e. none of the above are correct answers考试大(www.Examda。com)
ans: e
4. quality assurance
a. refers to the prevention of product defects
b. is an auditing function that provides feedback to the project team and client about the quality of output being produced.
c. is the technical process that include the construction of control charts which specify acceptability limits for conforming output.
d. a and b.
e. b and c
ans: b
5. which of the following communication media is least accepted by organizations?
a. tactile
b. audio
c. extrasensory
d. visual来源:考试大
e. olfactory
ans: c
6. formal written communication is mandated for which of the following?
a. scope changes not part of the original project
b. taking exception to a specification
c. procurement of raw materials
d. all of the above.
e. a and b only
ans: d
7. in performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:
a. work breakdown structure
b. milestone review and schedule technique
c. cost/schedule control system
d. planning programming budget system
e. program and evaluation review technique
ans: a
8. in the project environment, the individual ultimately responsible for quality control is:
a. the line workers who must strive "to do things right the first time" to avoid quality problems.
b. the company's quality control manager who must work with the project members to ensure the quality control program is effective.
c. the head of the production department who retains ultimate quality control responsibility for all the company's projects.
d. the project manager who has ultimate responsibility for the entire project.
e. the customer who must ensure that he is receiving a quality product from the vendor.
ans: d
9. in which organizational form do project managers usually get to know the employees well enough to provide an input into their performance
review?
a. expediter
b. coordinator来源:考试大网
c. pure project
d. matrix
e. line-staff
ans: c
10. the critical path in a schedule network is the path that:
a. takes the longest time to complete
b. must be done before any other tasks
c. allows some flexibility in scheduling a start time.
d. is not affected by schedule slippage
e. all of the above.
ans: a
11. the use of the project reports:
a. are not necessary on small projects
b. provides a means whereby various levels of authority can judge project performance
c. provides insight into project areas and the effectiveness of the control systems
d. all of the above
e. b and cwww.Examda.CoM
ans: e
12. you must produce 27 widgets. you can only produce 9 widgets per production run. each production line setup costs $1000. each widget
consumes $10 worth of material and $5 worth of labor. what is the total fixed cost for producing the widgets.
a. 3000
b. 27000
c. 27270
d. 1335
e. 1000
ans: e
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1山西连续两年投资总量超万亿
- 2剪板机安全要求
- 3一级建造师管理与实务:传力杆的固定安装方法
- 42015年安全工程师生产管理知识模拟精选(15)
- 5郑东新区宋庆龄雕像造价1.2亿未完成却被拆
- 6天津公布2015安全工程师报名时间:6月15日至6月29日
- 7建筑信息化模型的数据转换
- 82015年一级建造师《工程经济》第二篇冲刺讲义(3)
- 9【最新】天津人事考试网公布2015年安全工程师报名入口
- 10安全工程师资料
- 11厦门杏林大桥移动模架高空后移解体拆除工艺
- 122015年陕西安全工程师考试报名时间为4月28日-5月24日
- 13采购人评委地位与作用(上)
- 142015招标师《法规与政策》考前应试知识点:评标专家的选择
- 15钢筋混凝土预制沉井施工
- 16工程硕士专业学位之车辆工程领域简介
- 17安全工程师《安全生产技术》:专项安全施工组织设计的要点
- 18一级建造师管理与实务复习要点:警示标志
- 192015年咨询工程师《宏观经济政策与发展规划》每日一练(9.26)
- 20冶金安全生产事故的主要分析技术及方法
- 21[中天]建筑工程实测实量操作手册(结构、砌筑、抹灰)
- 22幕墙立柱是一层一根吗
- 23一种基于人员定位的矿井综合通信系统
- 24怎样快速通过考试
- 25中国某大剧院给排水设计实例 5P
- 262015年二级建造师《法规及相关知识》每日一练(2.19)
- 272013年二级建造师《建筑》:工程价款结算争议处理
- 282015年一级建造师《法规》:民法(2)
- 292015年注册咨询工程师《工程咨询概论》模拟题(40)
- 302015年造价工程师《理论与法规》讲义精髓(9)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼