PMP认证考试练习题及参考答案(三十六)
A Capital budgeting process.
B Overhead rates.
C Contracts and administration costing system.
D Fringe benefits packages.
E None of the above. www.Examda.CoM
ans:B
2 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.
A Increase, increase.
B Increase, decrease.
C Decrease, decrease.
D Decrease, increase.
E Remain the same, return to customer.
ans:E
3 The most effective means of determining the cost of a project is to price out the _____.
A Work breakdown structure.
B Linear responsibility chart. 来源:考试大
C Project charter.
D Scope statement.
E Management plan.
ans:A
4 The most expensive phase of life cycle costing is:
A R & D.
B Applied research.
C Production
D Operations and support.
E Termination.
ans:D
5 A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).
A Parametric
B Definitive.
C Budget
D Bottom up.
E Top down.
ans:C
6 The most precise or accurate estimate for determining project costs is the _____ estimate.
A Definitive.
B Analogy
C Budget
D Modified standards.
E Rule of thumb.
ans:A
7 Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.
A Definitive, bottom up.
B Analogy, top down.
C Parametric, bottom up.
D Parametric, top down. www.Examda.CoM
E Analogy, bottom up.
ans:D
8 A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight, storage and loss.
A Inventory control.
B Materials management.
C Procurement.
D All of the above.
E A and C only.
ans:B
9 There are two major types of reserves used on projects. The _____ is for (usually major) scope changes that were not considered as part of the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.
A Management reserve, unplanned allowance fund.
B Management reserve, contingency.
C Contingency fund, management reserve.
D Unplanned allowance fund, budgetary reserve.
E Unplanned reserve, planned reserve.
ans:C
10 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:
A Overhead rates, labor rates and material costs.
B Overhead rates, schedule slippages, and rework.
C Rework, cost-of-living adjustments, and overtime.
D Material costs, shipping cost, and scope changes.
E Labor rates, material costs, and cost reporting.
ans:A
11 The three most common types of project cost estimates are:
A Order of magnitude, parametric, and budget.
B Parametric, definitive and top down.
C Order of magnitude, definitive and bottom up.
D Order of magnitude, budget and definitive.
E Analogy, parametric and top down.
ans:D
12 The work breakdown structure, the work packages, and the company's accounting system are tied together through the:
A Code of accounts.
B Overhead rates.
C Budgeting system.
D Capital budgeting process.
E All of the above.
ans:A
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1工程咨询概论考试点:工程咨询服务的质量管理
- 2监理工程师考题精选——质量控制(七)
- 3水泥的特性和有特殊要求的混凝土
- 42015年咨询工程师《项目组织与管理》模拟题(20)
- 5全球定位系统和导线测量在工程中的分级控制
- 6陕西:省住房和城乡建设厅兵分三路督察重点示范镇建设
- 72015二级注册消防工程师的考试报名时间
- 8二级建造师考试复习总结:路基冬期施工技术
- 9注册安全工程师的前景
- 102015年咨询工程师《工程咨询概论》每日一练(8.7)
- 11湖北孝感建行分行积极推进造价咨询业务
- 12[广东]2014年建设执法监察工作要点
- 13杭州15条历史文化街区完成保护整治 小巷再现"前世今生"
- 14监理工程师考试2015年《工程质量与进度控制》练习题(3)
- 152015年咨询工程师《项目决策分析与评价》每日一练2.7
- 162015年10月二级建造师考试通关宝典
- 172012一级建造师《市政工程》考试用书相关答疑(9)
- 182015年安全工程师《生产技术》练习题(8)
- 19室内给排水施工方案
- 202015年咨询工程师《宏观经济政策与发展规划》每日一练(12.31)
- 21采购实务:政府采购操作程序探讨
- 222015年监理工程师应试指南——《质量控制》
- 23高速工程堑边坡生态防护工程施工组织方案
- 242015年咨询工程师《项目决策分析与评价》每日一练6.11
- 25造价工程师技术与计量(土建)复习资料——面层
- 26造价工程师案例分析复习要点:净现金流量
- 27遂资眉高速仁寿段油房湾隧道右洞正式贯通
- 28安全工程师《安全生产管理》知识:安全生产投入1
- 29什么是泥石流
- 30高速公路绿化工程施工组织设计
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼