PMP项目管理:项目风险管理练习题4
1.When the risk event probabilities are multiplied by their respective estimated risk event values (in dollars) and are then added together, the sum represents the:
A.Project manager ’s risk aversion quotient
B.Total project risk events
C.Expected monetary value of the project’s risk
D.Scope planning
当风险事件概率乘以他们相应的风险事件估计价值 ( 以美元计) ,然后加在一起的总和表示:
A.项目经理的风险厌恶系数
B.总的项目风险事件
C.项目风险的预期估价
D.范围规划
2.Which of the following utility functions reflect risk aversion?
A.Uniform
B.Increasing rate
C.Decreasing rate
D.Exponential
下列哪一个效用函数反映着厌恶风险?
A.一致性
B.递增比率
C.递减比率
D.指数
3. A project manager states, “I know that the risk exists and am aware of the possible consequences.I am willing to wait and see what happens.I accept the consequences should they occur.” He /she is exercising the method of risk reduction.
A.Transfer
B.Avoidance
C.Mitigation
D.Assumption
某项目经理说,"我知道有风险存在,而且注意到其可能的后果我愿意等着看会发生什么事万一他们确实发生,我接受其结果" 他对于减少风险是在用什么方式
A.转移
B.回避
C.降低
D.接受
4. A project manager states, “I will take the necessary measures required to control this risk by continuously reevaluating it and developing contingency plans or fall-back positions.If the risk event occurs, I will take the appropriate actions.” He/she is exercising the method of risk reduction.
A.Transfer
B.Avoidance
C.Mitigation
D.Acceptance
某项目经理人说," 我将会采取必要的措施去控制风险, 通过不断地反复评估风险, 制定应变计划或重做
如果风险事件确实发生, 我将会采取适当的行动"该经理是在运用什么方式去减少风险
A.转移
B.回避
C.降低
D.接受
5.If a project manager has a very low tolerance for risk, he is said to be:
A.Risk averse
B.Risk tolerant
C.Risk reluctant
D.Methodical
如果一个项目经理对风险难以忍受,,他是:
A.厌恶风险的
B.能承受风险的
C.不愿意有风险的
D.有办法的
6.If the minimum payoffs of four different strategies A1, A2, A3, and A4 are –10, 15, 0, and –20 respectively, which strategy would a project manager choose, using the “maximin” or Wald criteria (risk avoide r)?
A.Strategy A1
B.Strategy A2
C.Strategy A3
D.Strategy A4
如果四个不同的策略 A1 A2 A3 和 A4 的最小报酬分别是-10,15,0, 和-20, 用” 最小最大化”或Wald 标准(避免风险), 项目经理会选择哪一个策略?
A.策略 A1
B.策略 A2
C.策略 A3
D.策略 A4
7.The iterative process that helps determine those risks that might affect the project and documenting their characteristics is known as:
A.Risk identification
B.Risk-handing
C.Lessons learned
D.Risk analysis
反复检查,以帮助决定哪些风险会影响项目,并记录风险的特性.这个过程被称为是:
A.风险识别
B.风险处理
C.经验教训学习
D.风险分析
8.Based on the data in the table below, which strategy has the highest expected value?
A.S1
B.S2
C.S3
D.S4
Payoff Table (Profit in Millions)
Strategy Scenario 1 25% Scenario 2 50% Scenario 3 25%
S1 80 50 120
S2 80 80 80
S3 160 120 -20
S4 20 40 20
S5 -20 0 -60
基于下表数据计算, 哪一策略有最高的期望值?
A.S1
B.S2
C.S3
D.S4
9.Risk can have a positive or negative impact on a project.Future events or outcomes that are favor able are called:
A.Risks
B.Opportunities
C.Benefits
D.Contingencies
风险对项目可能有正面或负面的影响
未来的事件或结果是有利的被称为:
A.风险
B.机会
C.受益
D.意外事件
10.Using the figure below, what is the probability that project1 will be selected and completed successfully?
A.50%
B.30%
C.60%
D.40%
用下面数字计算,项目1 将会被选择并且成功完成的概率是多少?
A.50%
B.30%
C.60%
D.40%
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1造价工程师案例分析复习资料——投标报价的原则
- 2涵洞、通道盖板预制安装施工工法
- 3造价工程师案例分析复习要点:短期借款和流动资金借款
- 4北京某综合楼地下室SBS防水施工方案
- 52015年喀什造价工程师准考证打印时间
- 6安徽蚌埠市非公组织廉洁文化取得阶段性成功
- 7审计署发布高速路审计公告 多结算工程造价等问题显现
- 8泵送混凝土的操作要求
- 9混凝土泵安全操作规程
- 10[四川]分离式双洞公路隧道施工组织设计(实施)
- 11温州护国寺修建工程的施工组织设计方案
- 12云南:大丽高速公路建设顺利推进
- 132015年咨询工程师《项目组织与管理》模拟题(28)
- 142015年郑州造价工程师考试报名时间为7月27日-8月8日
- 15某水厂建筑及构筑物图例
- 16某大厦室外景观工程施工组织设计60p
- 17易自燃厚煤层群适用放顶煤开采的瓦斯综合防治技术
- 182015年招标师考点辅导:广义的项目管理与狭义的项目管理
- 19钻孔灌注桩施工机具选择
- 202015年内蒙古注册安全工程师报名入口
- 212015年招标师复习项目管理与招标采购知识点(3)
- 22矿井雨季安全防水措施
- 23门窗工程通病防治及质量预控
- 242015年造价工程师《计价控制》第四章讲义(8)
- 252015年安全工程师《安全生产管理知识》练习题(10)
- 26安全工程师《生产法及法律知识》知识要点(12)
- 272015年监理工程师《合同管理》习题(19)
- 282015年安全工程师《安全生产技术》:液化气体的充装
- 29大型钢吊箱围堰整体船运吊装施工工法
- 30铜陵市2015年造价工程师考试5月24日至6月9日报名
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼