PMP认证考试练习题及参考答案(五)
1. there are two major types of reserves used on projects. the _____ is for (usually major) scope changes that were not considered as part of
the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.
a. management reserve, unplanned allowance fund.
b. management reserve, contingency.
c. contingency fund, management reserve.
d. unplanned allowance fund, budgetary reserve.
e. unplanned reserve, planned reserve.
ans: c
2. to determine what causes the majority of quality problems in a process, a very useful tool is the:
a. cause and effect diagrams.
b. flow chart.
c. control chart.
d. pareto chart.
e. trend chart.来源:www.examda.com
ans: d
3. which of the following is not part of contract administration
a. contract award
b. performance control
c. financial control
d. contract closeout
e. all of the above are parts of contract administration.
ans: a
4. a(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight,
storage and loss.
a. inventory control.
b. materials management.
c. procurement.
d. all of the above.
e. a and c only.
ans: b
5. expectancy theory as applied to project management implies that:
a. the team will work the hardest on those goals that are clearly explained by the project manager
b. the more rewards that the project manager provides, the better the performance of the team
c. team members will work hardest for those project goals that also bring satisfaction to personal goals
d. employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members
e. none of the above
ans: c
6. non-verbal communication includes:
a. body movement
b. gestures来源:考试大网
c. facial expressions
d. the way we move our hands
e. all of the above
ans: e
7. the formal invitation to submit a price for specified goods/services is usually referred to as:
a. request for proposal
b. request for quotation
c. tender invitation
d. bid invitation
e. a and b only
ans: b
8. the project scope/charter baseline includes:
a. summary of background conditions defining the project.
b. organization, authority and responsibility relationships.
c. functions to be performed.
d. resource requirement schedule including time estimates.
e. all of the above.
ans: e
9. which of the following is not an input to quality planning?
a. scope statement.
b. regulations.
c. work results.
d. standards.
e. quality policy.
ans: c
10. which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous
element has been completed?
a. pert
b. adm
c. pdm
d. all of the above.考试大(www.Examda。com)
e. a and c only.
ans: c
11. which of the following utility functions reflects risk-aversion:
a. uniform
b. increasing
c. decreasing
d. exponential
e. b and d only
ans: c
12. a deficiency in characteristics that render the quality of the material/service unacceptable is usually referred to as:
a. defective
b. defect
c. non-conformance来源:考试大网
d. poor workmanship
e. lack of fitness for use
ans: c
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1《宏观经济政策与发展规划》知识点:建设工程合同的内容
- 2隧道综合整治施工组织设计
- 3人工挖孔桩施工工艺
- 42008年注册安全工程师考试注册管理(考试介绍)
- 5安全工程师生产法复习资料——资质申请时间
- 6搅拌车点火系统低压电路故障检修
- 72015年咨询工程师《项目决策分析与评价》每日一练(8.14)
- 82015年咨询工程师《政策与规划》每日一练(6.9)
- 9广州南沙投资82亿开建灵山岛尖综合项目
- 10三合一自粘防水卷材的施工工艺
- 11一级建造师管理与实务复习要点:投标人
- 12贵广铁路某隧道实施性施工组织设计
- 13超高脚手架沉陷事故处理方案
- 142008年安全工程师考试《安全生产管理知识》习题二十三
- 15在土方填筑施工中,为什么要控制填土的含水量
- 162012年pmp模拟试题及答案十套
- 17特种作业人员
- 18搅拌车发动机保养几个要点
- 19工程造价基础知识建设项目设计概算:建设项目总概算的编制
- 20一级建造师项目管理复习要点:工程网络计划
- 212015年招标师考试重点归纳:招标质量
- 22造价员《土建工程》基础知识:墙厚确定
- 23道路软基处理方法
- 24606米武汉绿地中心跃出地面 开始地上主体结构施
- 25佛山市2008年度造价工程师执业资格考试4月28日至5月23日报名
- 26河北省在全国率先推行施工企业预选名录制度
- 27普通混凝土用砂的化学法碱活性试验步骤
- 282010年PMP美国项目管理考试习题及答案九十八
- 29二灰碎石结构层施工
- 30安全工程师答疑精华:行政处罚的原则
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼