1. overlapping activities on a project, such as design and construction, is referred to as:
a. fast tracking
b. risk conversion.
c. parallel management.
d. process improvement.
e. synchronous manufacturing来源:考试大网
ans: a
2. the major reason why a project manager would use written instead of oral communication is:
a. documentation
b. feedback
c. cost
d. barrier elimination
e. all of the above.
ans: a
3. the scope management provides:来源:考试大网
a. a basis for future decisions about the project.
b. a baseline to accomplish verification measures.
c. a baseline to evaluate potential scope changes.
d. all of the above.
e. b and c only.
ans: d
4. total project risk can be defined as:
a. the sum of the probabilities of project risks events times the sum of consequences of those risks
b. the sum of the products of each project risk event times its consequences
c. the sum of the consequences of all project risk events
d. the sum of the probabilities of all project risk events
e. 1 - the sum of the probabilities of all project risk events.
ans: b
5. which of the following statements about the cost of quality are true?
a. the cost of quality is the expense of nonconformance to requirements and specifications.
b. the cost of quality are mostly the direct responsibility of workers who are manufacturing the product.
c. quality control programs should be implemented when the cost of quality are deemed affordable by management.
d. a and b.来源:考试大
e. a and c
ans: a
6. a line manager who is asked to wear two hats and function as a project manager at the same time is likely to exercise:
a. authority
b. power
c. influence
d. all of the above]
e. a and b only
ans: d
7. including the customer in the process of project planning is:
a. slow and counterproductive.
b. essential in the definition and documentation of project goals.
c. necessary, but of limited value.
d. unnecessary because project goals are defined in the proposal stage.
e. none of the above.
ans: b
8. it is argumentative whether project managers actually control costs. which of the following is the most common element over which the
project manager may have some degree of control?
a. direct labor dollars
b. direct labor hours.www.Examda.CoM
c. overhead rates.
d. procurement costs.
e. none of the above.
ans: b
9. most quality problems:
a. originate in the quality department where the ultimate responsibility for quality rests.
b. originate on the shop floor because of waste and product rework.
c. are the results of management inattention to potential quality improvement ideas.
d. could be eliminated if shop supervisors monitored their work more closely.
e. a and b
ans: c
10. the "buy or make" decision is usually made during the:
a. acquisition cycle
b. contract evaluation cycle
c. requirements cycle
d. pre-award cycle
e. at any time that is convenient for the project manager
ans: c
11. the logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to
as:
a. slackwww.Examda.CoM
b. free float.
c. restricted float.
d. level float.
e. lag
ans: e
12. which of the following actions is an example of risk response:
a. adjust project parameters (scope, time, quality ...)
b. reduce the probability of potential project risk events
c. reduce the consequences of potential project risk events
d. wait until a problem actually happens, then deal with it in the most effective and efficient manner.
e. a, b and c only
ans: e
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 12015年咨询工程师《宏观经济政策与发展规划》每日一练8.27
- 2安全工程师案例分析题(十)
- 32015造价工程师《理论与法规》辅导讲义(18)
- 4园路样式二
- 5安全工程师考试《法律法规》习题班讲义精选(50)
- 6信息化管理在工程项目管理中的应用
- 72015年监理工程师《建设工程三大控制》练习题(55)
- 8造价工程师技术与计量复习要点:装修
- 9注册消防工程师考试复习要有坚定的信念
- 10在正常使用条件下,保温工程的最低保修期限为几年
- 11【招标师考试】项目管理与招标采购第三章:水路运输
- 12湖南:今年新建干线公路2000公里
- 132012一级建造师《公路工程》:工程量清单的含义
- 142012一级建造师《公路工程》:工程变更的基本类型
- 15框架结构的施工要求
- 16催化重整装置安全设施设置的考虑
- 172015招标师考试:招标采购专业实务第十章详解2
- 18焦炭后市弱势下行趋势不变
- 19某住宅小区景观工程施工组织设计
- 202015年造价员基础知识:炉墙的砌筑
- 212013年二级建造师法律法规及相关知识考试用书及资料
- 22新旧管道交叉处加固和施工方案
- 23一级建造师工程经济复习要点:资本金现金流量表
- 24Project Controlling与建设项目管理的相同点
- 252015.6.20咨询工程师每日一练免费在线测试
- 26贵州省2015年造价工程师考试报名时间确定:6月10日至30日
- 27一级建造师管理与实务复习要点:土方回填
- 282013年二级建造师《建筑》:混凝土工程
- 292015一级建造师《水利水电工程管理与实务》讲义(13)
- 302015招标师考试《项目管理与招标采购》模拟试题及答案1
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼