PMP认证考试练习题及参考答案(七)
1. which of the following is associated with a buyer's request for material to meet a particular need:
a. material warranty
b. material guarantees
c. implied warranty of salability
d. implied warranty of fitness for a particular purpose
e. a and c onlywww.Examda.CoM
ans: d
2. a project manager trying to communicate accurately to the team should use:
a. the language of the team members
b. the language of the project manager
c. non-verbal methods
d. written memos
e. all of the above.
ans: a
3. an advertiser who uses a movie or sports star to endorse a product is trying to use power.
a. expert
b. legitimate
c. reward
d. influential
e. referent
ans: e来源:考试大
4. control chart theory is based on the differentiation of the causes of variations in quality. variations may be produced by assignable causes.
all of the following are examples of assignable causes except:
a. differences among machines.
b. differences among workers.
c. differences among materials.
d. differences in each of these factors over time.
e. none of the above (all are examples)
ans: e

5. giving a part of project work to a contractor is an example of:
a. risk mitigation
b. risk assignment
c. risk delegation
d. risk deflection
e. risk assumption来源:www.examda.com
ans: d
6. proper implementation of project management will guarantee that:
a. budgets will be met.
b. schedules will be adhered to.
c. quality/performance will be met.
d. the project will be a success.
e. none of the above.
ans: e
7. the most effective means of determining the cost of a project is to price out the _____.
a. work breakdown structure.
b. linear responsibility chart.
c. project charter.
d. scope statement.
e. management plan.
ans: a
8. which method shown below is acceptable for reducing cost or shortening the schedule?
a. "crashing"
b. changing scope.
c. performing activities in parallel rather than in series.
d. all of the above.
e. a and c only.考试大(www.Examda。com)
ans: d
9. which of the following terms is used to describe the receipt issued by a carrier for items to be delivered to a third party:
a. free on board
b. receipt for merchandise
c. packaging list
d. loading list
e. bill of lading
ans: e
10. a computer tape which contains historical project information is called ____ tape.
a. database
b. baseline.
c. archive.
d. lessons learned.
e. life cycle summary.
ans: c
11. according to herzberg, which of the following is a motivational factor?
a. pay
b. hygiene needs
c. achievementwww.Examda.CoM
d. working conditions
e. vacation time
ans: c
12. communication in both project and non-project-driven organizations should occur in directions.
a. one
b. two
c. three
d. four
e. five
ans: e