PMP认证考试练习题及参考答案(十一)
1. _____ is associated with a buyer's request for materials or equipment to meet a particular need or accomplish a specific purpose.
a. express warranty
b. implied warranty of merchantability
c. implied warranty of fitness for a particular purpose
d. prescribed warranty
e. none of the above.
ans: c来源:www.examda.com
2. adm is an activity-on-arrow method. in this method, a dummy activity:
a. denotes a critical path relationship.
b. denotes any dependency relationship.
c. shows slack.
d. identifies customer deliverables dates.
e. identifies customer team meeting dates.
ans: b
3. an informal communication network on a project and within an organization is called a(n):
a. free upward flow
b. free horizontal flow
c. unrestricted communication flow
d. grapevine
e. open networkwww.Examda.CoM
ans: d
4. by which process may an unsuccessful supplier seek remedy for unjust awards?
a. contract dispute
b. stop work order
c. bid protest
d. coffective action
e. none of the above.
ans: c
205. risk classified as unknown unknowns (i.e., those which cannot be identified or evaluated):
a. should be deflected to the contracting officer
b. should be handled via contingency allowances
c. should be ignored, since they cannot be identified
d. should be ignored, since they are not covered in the project risk assessment
e. c and d
ans: b
6. the "zero defect" concept was proposed by:
a. deming
b. juran
c. crosby
d. tagushi
e. a and d only来源:考试大
ans: c
7. the major difference between project and line management is that the project manager may not have any control over which basic
management function?
a. decision-making
b. staffing
c. rewarding
d. tracking/monitoring
e. reviewing
ans: b
8. which of the following planning considerations is often overlooked?
a. planning for project termination.
b. qualified project manager assignment.
c. insuring top management support.
d. clearly defined tasks.
e. all of the above.
ans: a
9. a recurring communication pattern within the project organization or company is called a:
a. free-form matrix
b. structured matrix
c. network
d. rigid channel
e. none of the above.来源:www.examda.com
ans: c
10. during a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12%
of the work scheduled to this point of time. you can therefore conclude that:
a. the project will be completed late.
b. the critical path has been lengthened.
c. the costs are being overrun.
d. overtime will be required to maintain the original critical path.
e. none of the above.
ans: e
11. once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. this will
provide information on the _____ and identification of the _____ .
a. slack for each activity, critical path.
b. slack for each activity, high risk activities.
c. manpower shortages, high risk activities.
d. high risk activities, non-critical paths.
e. manpower availability, contingency plans.
ans: a
12. risk can be divided into two basic types; business risk and pure (or insurable risk). of the following, which one(s) fall(s) under business risk?
a. liability loss
b. direct property loss
c. profit loss
d. personnel-related loss
e. b and c
ans: c
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1氨分解制氢站安全注意事项
- 2[贵州]07安全工程师考试5.15起报名
- 3某高速公路绿化工程施工组织设计方案
- 4浙江某展览馆施工现场临水临电平面布置图
- 52015年招标采购专业实务模考练习题五
- 6喷锚支护锚杆怎么布置?
- 7步行街绿化景观工程施工组织设计
- 8一级建造师管理与实务复习要点:盖挖法施工顺序
- 9青岛某综合楼内装修工程冬季施工质量控制措施
- 10广东推进名镇名村建设规划编制
- 11防水混凝土的试配申请有何要求
- 12公路桥梁各分项工序施工方法
- 13[成都]新都斑竹园镇一在建工地坍塌 致工人1死2伤
- 142015年招标师法律法规高频考点:投标有效期的确定
- 152015年安全工程师考试题库《生产技术》(14)
- 16全站仪后方交会在中小型矿井定向中的应用探讨
- 17一级建造师《建设工程经济》复习资料整理(14)
- 18吕梁环城高速公路某隧道施工组织设计(2011年 双洞 分离式断面)
- 192012一级建造师:工程量清单计价模式下招投标阶段的工程
- 202013年二级建造师《施工管理》每日一练(5.13)
- 21PMP认证考试练习题及参考答案(十九)
- 222015年造价员考试《基础知识》重点:控制系统的种类
- 236%HEC固结土施工方法
- 242008年安全工程师考试《安全生产技术》习题二十五
- 25杭州引入“空中城管” 违建证据被飞机“航拍”
- 262015造价员《土建工程》土木工程材料:防水材料
- 27[福州]会展中心临时用电、给排水及消防平面布置图
- 282013年海南二级建造师注册证书、执业印章遗失补办申请表
- 292015一级建造师《机电工程》 起重技术(2)
- 30全国工程质量治理两年行动电视电话会议昨日召开
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼