PMP认证考试练习题及参考答案(二十八)
1 A task-oriented family tree of activities is a:
A Detailed plan.
B Linear responsibility chart.
C Work breakdown structure.
D Cost account coding system.
E Work package description.
ans:C
2 Management plans include all of the following except:
A Organization of project.
B Job descriptions.
C Policies and procedures.
D Linear responsibility charts. http://ks.examda.com
E Scope baseline.
ans:E
3 A comprehensive definition of scope management would be:
A Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
B Approval of the scope baseline.
C Approval of the detailed project charter.
D Configuration control.
E Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
ans:A
4 The process of choosing/documenting the best approach to achieve the project objectives is part of:
A The scope baseline.
B Scope authorization
C Scope definition 来源:考试大
D Scope planning.
E All of the above.
ans:D
5 A completion of a local government study resides on your critical path. This would most likely be referred to as:
A Soft logic
B Hard logic
C An external dependency
D A mandatory dependency
E A lost cause
ans:C
6 Which of the following can affect network durations?
A Skills of the resource pool
B Calendar dates
C Constraints
D All of the above
E A and B only
ans:E
7 Sources for data on activity durations and resource requirements can be gathered from which of the following:
A Past project records (historical data)
B Commercial techniques (standard practices, rules of thumb)
C Past project team members knowledge (experience, oldtimers)
D All of the above www.Examda.CoM
E A and C only
ans:D
8 The erection of foundation formwork before the placement of foundation concrete would be an example of a _____ dependency.
A Discretionary
B Mandatory
C External
D Soft logic
E Subcontracted
ans:B
9 "Hard logic" in the preparation of a network refers to:
A Discretionay dependencies
B External depenencies
C Mandatory dependencies
D All of the above
E A abd B only
ans:C
10 The difference between a project and a program is that:
A A program is made up of multiple projects
B A program requires at least three times longer to plan than a project
C A project is a one-shot deal while a program is on-going
D A and C
E B and C
ans:D
11 As a control tool, the bar chart (Gantt) methods is most beneficial for:
A rearranging conflicting tasks
B depicting actual versus planned tasks
C showing the outer dependencies of tasks
D A and C.
E A and D
ans:B
12 You are managing an internal project where a vice president from the user group is acting as the sponsor. You have just been informed by your team that the critical path has slipped by three weeks. You should:
A Immediately inform the sponsor and ask for advice
B Do nothing until the slippage occurs
C See the sponsor after you have evaluated alternatives, recommendations, and performed an impact analysis
D Look for someone to blame before you see the sponsor
E Inform your senior management of the problem and tell them that you will get back to them after you assessed the situation
ans:C
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1从细微之处判断搅拌车故障隐患
- 22015年安全工程师考试《事故案例分析》练习题(3)
- 3青海城镇化率今年力争达到50%
- 4安全工程师《安全生产管理》知识:安全检查的程序
- 5咨询工程师2015年考试《组织与管理》习题(1)
- 6建设专家建议贵州应多造山区拱桥 减少修路成本
- 7地铁永平路车站主体月底封顶
- 8安全工程师答疑精华:应急预案的主要内容
- 9宏观经济政策与发展规划知识点:建设工程监理的范围和规模
- 102015年安全工程师考试《安全生产技术》:检查和监测技术
- 11我国拟定地坪漆工程验收标准 或参考国外体系
- 122015招标师《法规与政策》考前应试知识点:投标有效期延长
- 13重庆出台地方一带一路意见 基建投资或达1.2万亿
- 14Ⅱ-型板式无碴轨道混凝土底座板施工工法
- 15山西某水泥厂施工平面布置图(CAD版本)
- 16住建部发农村危房现状调查通知
- 17某污水深度处理厂施工组织设计145P
- 182015年招标师《招标采购法律法规与政策》试题(1)
- 19现代咨询方法与实务知识点:融资主体
- 20监理工程师考试2015年《建设工程合同管理》习题(5)
- 21今年广东海洋经济总值有望破万亿元
- 222015年天水造价工程师报名时间为6月26日-7月26日
- 23工程咨询概论知识点:项目可行性研究
- 24造型复杂的高层建筑在不同施工阶段的整体提升脚手架的运用
- 25一级消防师考试用书
- 26江西九江市建设规划局为工程建设造价把关
- 27工程咨询概论知识点:工程咨询服务投标文件的编制
- 28造价员考试土建工程重点解析:钢筋工程
- 292015年咨询工程师《工程项目组织与管理》每日一练7.2
- 302015年咨询工程师《项目决策分析与评价》每日一练(7.2)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼