PMP认证考试练习题及参考答案(二十九)
1 Which of the following impacts the critical path?
A Changing the task duration.
B Reduce the free float of an activity.
C Executing a backward pass
D A or B
E None of the above.
ans:A
2 The range of time allowed for an activity to be completed in is the _____.
A Planned time (Duration).
B Float time (LS - ES, or LF - EF).
C Critical time (when ES = LS, or EF = LF). 来源:www.examda.com
D Scheduled time (LF - ES).
E Event.
ans:D
3 Free float is the amount of time that an activity may be delayed with out affecting the _____.
A Early start of the succeeding activities.
B Late start of the succeeding activities.
C Project finish.
D Cost of the project.
E None of the above.
ans:A
4 Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.
A 0.5
B 1
C 1.8
D 2.2
E 2.8
ans:C
5 In crashing a task, you would focus on:
A As many tasks as possible.
B Non critical tasks. http://ks.examda.com
C Accelerating performance of tasks on critical path.
D Accelerate performance by minimizing cost.
E A and D.
ans:C
6 Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task
A 8
B 8.8
C 9.1
D 9.7
E 10.5
ans:B
7 Using the WBS in the Special window, an instance of a work package is:
A Build house
B Excavate
C Prepare Foundation
D B and C
E None of the above 来源:考试大网
ans:E
8 All of the following are categories of a milestone in a schedule except:
A End date.
B Contract dates.
C Key events scheduled.
D Imposed dates.
E Task duration.
ans:E
9 The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A Increases.
B Is not affected by
C Does not require
D Is heavily dependent upon
E Is the only means of determining
ans:D
10 Excessive flexibility in specifying requirements will _____ the likelihood of time overruns.
A Reduce.
B Eliminate.
C Double
D Increase
E Not affect
ans:D
11 The key purpose of project control is to:
A Plan ahead for uncertainties.
B Generate status reports.
C Keep the project on track.
D Develop the project road map.
E All of the above. 来源:考试大网
ans:C
12 Fast tracking means to:
A Speed up a project through parallel tasks.
B Swap one task for another.
C Reduce the number of tasks if possible.
D B and C.
E None of the above.
ans:A
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1监理工程师考试2015年《工程质量与进度控制》练习题(8)
- 22015年安全工程师考试《安全生产法及相关》练习题(16)
- 3一级建造师工程经济复习要点:招标代理费
- 42015年咨询工程师考试《宏观经济政策》练习习题(10)
- 5某图书馆管线工程施工组织设计
- 6工程造价基础知识:建设工程施工合同争议的解决办法
- 72015年招标师《招标采购案例分析》辨析性问题(3)
- 82015年咨询工程师《工程项目组织与管理》每日一练(2.6)
- 92012一级建造师《建设工程经济》仲裁程序
- 10造价工程师复习资料:设计阶段工程造价计价与控制的重要意义
- 11[济南]当地旱情严重 致白云湖目前仅剩半湖水
- 122015年招标师《专业实务》:招标中碰到的几个问题
- 132015年招标师:招标采购专业实务精选习题48
- 142013年吉林二级建造师注册证书、执业印章污损更换申请表
- 152015招标师考试:招标采购专业实务详解37
- 16别墅小区外围巡更小路施工组织方案
- 17小型混凝土搅拌车的搅拌筒
- 182013年西藏二级建造师注册证书、执业印章遗失补办申请表
- 19滑坡发育的外部条件是什么
- 20西宝客专二季度铺轨年底实现通车运营
- 212008年监理工程师《建设工程合同管理》习题33
- 222015年咨询工程师《工程咨询概论》练习题20
- 232015年招标师《专业实务》:甲方招标主要流程和评价方法
- 24新建铁路南宁至广州线某标段某隧道(实施)施工组织设计
- 252015年山西安全工程师报名条件
- 26浙江临海四措施清理农村违章建筑
- 27招标师法律法规:民事权利
- 28湖北铁路建设提速 江汉平原货运铁路明年开工
- 292015年鹤岗造价工程师准考证打印时间
- 30一级建造师考试精华总结:评标的准备与初步评审
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼