2010年PMP美国项目管理考试习题及答案三
QUEST The scope statement provides
A A basis for future decisions about a project.
B A baseline to accomplish verification measures.
C A baseline to evaluate potential scope changes.
D All of the above
E B and C only
参考答案:D
QUEST A work breakdown structure:
A assures all work is identified.
B subdivides the project into manageable segments.
C provides the project sponsor with a time-phase task summary.
D both A and B.
E All of the above.
参考答案:D
QUEST Budgetary estimates are the output of the _____ phase(s) of the project.
A conceptual
B development
C implementation
D finish
E All of the above.
参考答案:B
QUEST Which of the following are included in the Acquisition phase(s) of the project life cycle.
A concept and development
B development and planning
C execution and phase-out
D planning and implementation
E concept and planning
参考答案:C

QUEST The scope statement provides
A A basis for future decisions about a project.
B A baseline to accomplish verification measures.
C A baseline to evaluate potential scope changes.
D All of the above
E B and C only
参考答案:E