PMP认证考试练习题(三)(中英文)
1. In fixed price contract which of the following holds true?
The seller agrees to use his best effort to fulfill the contract within the estimated contract amount.
The seller agrees to perform a service or furnish supplies at the established contract price.
If the amount of the contract is exceeded the seller is not obligated to perform further unless the buyer increases the funds.
More risk is placed on the buyer.
在固定价格合同中以下哪一条是正确的?
卖方同意在估算合同总量内尽最大努力履行合同
卖方同意在确定的合同价格上提供服务或供应
除非买方提高金额,若超出合同额卖方不负责履行超出部分
买方承担较大风险
2.If the project was supposed to have $1.000worth of work accomplished, but only completed $850 worth of work, what is the Scheduled Variance?
$150
$1.500
Cannot calculate from the information provided
.-$150
若项目完成预计价值$1.000,但仅完成$850的工作, 则进度偏差为:
$150
$1.500
以上资料无法计算
-$150
3.Using the table below, what is the Present Value of an annual expenditure of $4,000per year over the next three years at 10% pre year?
YearPresent Value of $1 at 10%
Present Value of $1 at 12%
1
0.909
0.893
2
0.826
0.797
3
0.751
0.712
4
0.683
0.636
-$9,608
-$7,206
_$9,944
$6,551
运用下表,计算年金流出流量为$4,000三年后的现值(利率10%/年).
年度$1在10%的利率下现值
$1在12%的利率下现值
1
0.909
0.893
2
0.826
0.797
3
0.751
0.712
4
0.683
0.636
-$9,608
-$7,206
_$9,944
$6,551
4. The initial cost of your project is $25,000, which will save the company $6,000 per year for the next four years. Using the above table. If your company wants a 12% ROI, what is the NPV of the project?
-$1,000
_$6,772
+$1,758
+$6,772
你的项目的初始费用为$25,000,而在今后的四年中每年将为公司节省$6,000,运用上表,若你的公司想获得12%的投资回报(ROI),则该项目的NPV净现值是:
-$1,000
_$6,772
+$1,758
+$6,772
5. ABC company commonly used Sum of the Years method to calculate depreciation on assets. They purchased a computer which cost $15,000, knowing they can sell it at the end of three years for $3,000. How much depreciation is taken the third year?
$4,000
$2,000
$7,500
$2,500
ABC公司通常使用年数和计折旧法计算资产折旧. 他们购买了一台价值$15,000的计算机,在第三年末该机可以$3,000的价格出售,则第三年所提的折旧为:
$4,000
$2,000
$7,500
$2,500
6. Your company has established a reward and recognition system for its project management professionals. Project cost performance is used as a criterion to determine rewards. What should you do to ensure that rewards reflect actual performance?
Consider overtime work as part of the job
Prepare a cost baseline
Use earned value management to monitor performance
Estimate and budget controllable and monitor performance
你们公司为项目管理的专业人士建立了一套奖励与考评系统. 项目成本业绩即是决定奖励的标准之一. 为了确保所给出的奖励能真正反映实际的业绩,你应该采取什么措施?
将加班视为工作的一部分
设定一个成本基线
利用挣值管理来监控业绩
对可控和不可控成本分别做出评估和预算
7. On a small project, one of the vendors informs the PM that he will substitute a better quality pipe for the pipe included in the initial plan since the pipe originally quoted is unavailable. Due to circumstances, the vendor indicated there would be no additional cost to the project. He also informs the PM that, due to a slight delay in delivery of the pipe, he will work on another task ahead of schedule. Where will the PM record these modifications?
WBS
Cost change control
Scope change control
Project schedule
A & d
在一个小项目中,一个供应商通知项目经理他将用高质量的管道替代原有管道,此方案放到立项计划里,因为管道的原先的报价没有. 鉴于这种情况,供应商提出他们不增加项目成本. 他同时告诉项目经理因为管道有一点延迟,他将做其他超出进度的工作. 项目经理将把此变更记在那里?
工作分解结构
成本变更控制
范围变更控制
项目进度
A 和 d
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 12015年造价工程师考试《计价控制》第二章讲义(3)
- 2市政公用工程工程量清单计价的具体内容
- 3二级建造师考试复习总结:框支承玻璃幕墙制作安装
- 4成都某住宅项目防水施工方案
- 5浅谈陀螺经纬仪在矿山测量中的应用
- 6造价工程师工程计价复习要点:工程索赔计算
- 72015年监理工程师《建设工程合同管理》练习题(87)
- 8写字楼消防安装工程施工组织设计 27P
- 92015咨询工程师考试《现代咨询方法与实务》试题(2)
- 10沪昆铁路客专铺轨基地春节后到达首列长轨
- 11安全工程师辅导资料:影响电力企业安全的内外因1
- 122015年安全工程师考试《安全生产法及相关》(30)
- 132015年安全工程师考试《管理知识》模拟题(81)
- 142015年咨询工程师考试《政策与规划》考点:项目管理职能
- 15造价工程师建设工程造价管理复习资料——英国工程造价管理
- 16广西第二批农村危房改造百分百开工
- 172015年招标师考试《案例分析》考前提高试题10
- 18某市劳动就业服务中心消防工程施工组织设计56P
- 19某大桥水下基础施工
- 202015年咨询工程师《宏观经济政策》练习题(45)
- 21黑龙江首个抽水蓄能电站项目筹备期工程6个标段全部实现开工建设
- 222015年二级建造师《建筑》:基坑支护安全检查评分表
- 23TGPMS:中国工程项目管理信息化的“旗舰”
- 24安全工程师安全生产技术复习要点:车辆伤害
- 25《项目组织与管理》知识点:由专业化机构进行项目管理的模式
- 262015一级建造师《铁路工程》复习指南(15)
- 27[兵团]2007年注册安全工程师考试成绩11月16日起网上查询
- 28特殊边坡绿化有几种
- 292015年咨询工程师《工程咨询概论》每日一练12 .6
- 302015年咨询工程师考试《概论》模拟练习题(8)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼