PMP美国项目管理认证的模拟考试的样题6
A. an exchange of information.
B. providing written or oral directions.
C. consists of senders and receivers
D. effective listening.
E. All of the above
ANS: E
2. Fixed Price contracts place more risk on the:
A. owner
B. buyer
C. seller
D. contractor
E. C or D
ANS: E
3. Life cycle costing is the total cost to the customer for the acquisition and
ownership over its full life. Life cycle costing categories include the cost
of _____, _____, and _____.
A. R & D, maintainability, operation and support.
B. R & D, production, operation and support.
C. Acquisition, operations, maintenance.
D. Production, operations, maintenance.
E. None of the above
ANS: B
4. Management By Objectives assumes that the team:
A. is receptive to an unstructured environment.
B. does not require close supervision.
C. possesses a self directed philosophy
D. identifies with project objectives.
E. All of the above.
ANS: E
5. Quality may be defined as:
A. conformance to requirements.
B. fitness for use.
C. continuous improvement of products and services
D. appeal to the customer
E. All of the above except B
ANS: E
6. Since risk is associated with most projects, the best course of action is
to:
A. cover all project risks by buying appropriate insurance
B. ignore the risks, since nothing can be done about them and move forward with
the project in an expeditious manner.
C. avoid projects with clear and present risks
D. eliminate all known risks prior to the execution phase of the project
E. identify various risks and implement actions to mitigate their potential
impact
ANS: E
7. The process of choosing/documenting the best approach to achieve the project
objectives is part of:
A. The scope baseline.
B. Scope authorization
C. Scope definition
D. Scope planning.
E. All of the above.
ANS: D
8. Time management is the allocation of time in a project’s life cycle through
the process of:
A. Planning
B. Estimating.
C. Scheduling.
D. Controlling
E. All of the above.
ANS: E
9. A comprehensive definition of scope management would be:
A. Managing a project in terms of its objective through the concept,
development, implementation, and termination phases of a project.
B. Approval of the scope baseline.
C. Approval of the detailed project charter.
D. Configuration control.
E. Approved detailed planning including budgets, resource allocation, linear
responsibility charts and management sponsorship.
ANS: A
10. Cost Plus Percentage of Cost contracts are more desirable for the:
A. owner
B. buyer
C. seller
D. contractor
E. C or D
ANS: E
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 12013年二级建造师《法规及相关知识》每日一练(1.21)
- 2关于升降脚手架安全监管几个重要问题的思考
- 3咨询工程师考试《工程咨询概论》考前自测题(31)
- 4招标师课程的网络更新进度
- 5居住区景观施工组织设计42p
- 6北京地铁十号线二期工程进入最后两站三区间动车调试
- 72015年监理工程师考试理论与法规练习题(44)
- 8生产性企业采购环节的税收筹划
- 92015咨询工程师考试《工程咨询概论》模拟练习(2)
- 102015年安全工程师考试《安全生产管理知识》练习题(28)
- 11解析管理信息化常见的十大陷阱
- 122015年咨询工程师《工程咨询概论》每日一练(3.1)
- 13冬季里搅拌车底盘的保养
- 142015.5.8咨询工程师每日一练免费在线测试
- 15招标师相关考试经验
- 16决策与分析考点:绿化布置
- 17工程造价基础知识:工程造价资料
- 18福建:漳永高速公路完成投资8.1亿元
- 19三峡库区漂浮垃圾堆聚成山 场景触目惊人
- 20混凝土泵一系列国内领先技术
- 212015年安全工程师考试《安全生产管理知识》练习题(55)
- 22西部开发十年 广西水利建设投资达500多亿
- 232015年一级建造师考试《法规及相关知识》冲刺习题(7)
- 24真空预压法加固软基施工
- 25在瓦斯矿井进行火灾事故抢救的安全技术问题探讨(下)
- 262015招标师《招标采购案例分析》串讲讲义下载(4)
- 272015年招标师《专业实务》辅导:招标采购制度的起源
- 28某环境景观工程施工组织设计方案
- 29合同管理方面存在的问题(下)
- 30[湖北]厂房施工进度计划网络图和横道图(word版)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼