监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 签约案例 | 购买价格 | 在线试用 | 手机APP | 产品资料
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

PMP美国项目管理认证的模拟考试的样题6

申请免费试用、咨询电话:400-8352-114

1.  Communications  is  best  described  as:  
A.  an  exchange  of  information.  
B.  providing  written  or  oral  directions.  
C.  consists  of  senders  and  receivers  
D.  effective  listening.  
E.  All  of  the  above  
ANS:  E  

2.  Fixed  Price  contracts  place  more  risk  on  the:  
A.  owner  
B.  buyer  
C.  seller  
D.  contractor  
E.  C  or  D  
ANS:  E  

3.  Life  cycle  costing  is  the  total  cost  to  the  customer  for  the  acquisition  and  
ownership  over  its  full  life.  Life  cycle  costing  categories  include  the  cost  
of  _____,  _____,  and  _____.  
A.  R  &  D,  maintainability,  operation  and  support.  
B.  R  &  D,  production,  operation  and  support.  
C.  Acquisition,  operations,  maintenance.  
D.  Production,  operations,  maintenance.  
E.  None  of  the  above  
ANS:  B  

4.  Management  By  Objectives  assumes  that  the  team:  
A.  is  receptive  to  an  unstructured  environment.  
B.  does  not  require  close  supervision.  
C.  possesses  a  self  directed  philosophy  
D.  identifies  with  project  objectives.  
E.  All  of  the  above.  
ANS:  E  

5.  Quality  may  be  defined  as:  
A.  conformance  to  requirements.  
B.  fitness  for  use.  
C.  continuous  improvement  of  products  and  services  
D.  appeal  to  the  customer  
E.  All  of  the  above  except  B  
ANS:  E  

6.  Since  risk  is  associated  with  most  projects,  the  best  course  of  action  is  
to:  
A.  cover  all  project  risks  by  buying  appropriate  insurance  
B.  ignore  the  risks,  since  nothing  can  be  done  about  them  and  move  forward  with  
the  project  in  an  expeditious  manner.  
C.  avoid  projects  with  clear  and  present  risks  
D.  eliminate  all  known  risks  prior  to  the  execution  phase  of  the  project  
E.  identify  various  risks  and  implement  actions  to  mitigate  their  potential  
impact  
ANS:  E  

7.  The  process  of  choosing/documenting  the  best  approach  to  achieve  the  project
  objectives  is  part  of:  
A.  The  scope  baseline.  
B.  Scope  authorization  
C.  Scope  definition  
D.  Scope  planning.  
E.  All  of  the  above.  
ANS:  D  

8.  Time  management  is  the  allocation  of  time  in  a  project’s  life  cycle  through  
the  process  of:  
A.  Planning  
B.  Estimating.  
C.  Scheduling.  
D.  Controlling  
E.  All  of  the  above.  
ANS:  E  

9.  A  comprehensive  definition  of  scope  management  would  be:  
A.  Managing  a  project  in  terms  of  its  objective  through  the  concept,  
development,  implementation,  and  termination  phases  of  a  project.  
B.  Approval  of  the  scope  baseline.  
C.  Approval  of  the  detailed  project  charter.  
D.  Configuration  control.  
E.  Approved  detailed  planning  including  budgets,  resource  allocation,  linear  
responsibility  charts  and  management  sponsorship.  
ANS:  A  

10.  Cost  Plus  Percentage  of  Cost  contracts  are  more  desirable  for  the:  
A.  owner  
B.  buyer  
C.  seller  
D.  contractor  
E.  C  or  D  
ANS:  E  
发布:2007-03-02 10:58    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件