PMP项目管理:人力资源管理练习题3
1.Along with motivating the project team members toward the project goals, the project manager is expected to help team members fully understand that:
A.Conflicting orders may be given by different managers
B.Their future promotions depend solely on the project’s success
C.Technical knowledge is essential for project success
D.New projects do not come easily to project team members
2.The project manager’s success as a leader is dependent on their inter-personal skills and their:
A.Ability to lead, delegate and negotiate
B.Skill with which they can do the detailed technical tasks
C.Ability to conduct project team meetings
D.Hiring and firing skills
3.The right to command, issue order or act in the management of a project is called:
A.Power
B.Legitimate Power
C.Leadership
D.Influence
4.Dotted lines in organization charts mean:
A.The relationship may or may not exist depending on the nature of the organization
B.The relationship was not completely defined when the chart was finished
C.Informal authority and responsibility relationships
D.Unique and clearly defined relationships
5.As a project manager, you were able to convince the project team to follow certain courses of action based on your expertise on the subject.The team followed you because of your:
A.Referent power
B.Leadership
C.Influence
D.Expert power
6.Authority structure ranges from pure functional (traditional management) to dual authority (matrix) where the project manager and the functional manager both are present in the management equation.Matrix management is itself presented across a range of variations, from weak to balanced to strong.In context of project management, the key difference between a weak and a strong matrix structure is:
A.The culture of the company
B.The project manager ’s relative influence over the assigned functional resources
C.The size of the project relative to the company
D.The information flow
7.Which of the following types of information is not considered in the Linear Responsibility Chart (LRC)?
A.Who is responsible for the general and operational management of the project
B.Who must and may be consulted on each activity
C.Where the specialized responsibilities are allocated
D.When each activity will be concluded
8.The primary processes of human resources management are:
A.Organizational design, team building, resource planning, merit review and rewards
B.Organizational planning, staff acquisition, team development
C.Sponsor management, team development, project planning, stakeholder management
D.Staff planning, resource acquisition, team development, sponsor management
9.Herb has successfully kicked-off his project.Many of his team members actually work in the same building as Herb.Although several members are in distant cities, As project manager, it would be prudent and raise project awareness if Herb were to create a:
A.Video-conference once a week
B.Process to update the sponsor when the team felt it necessary
C.War room where the collocated team members could congregate to post schedules and update status
D.Project database of all project documentation that was accessible by all stakeholders over the intranet
10.Sheila has been managing her project for five months.She has receive d feedback from her functional manager and her project sponsor that she is not being an effective leader
from an organizational perspective.Which of the following best describes the behavior that might have generated this appraisal?
A.She has included functional managers in her project communications
B.Communications have been held only with stakeholders inside her organization
C.She has some conflicts with functional managers over resources
D.Organizational strategies have been loosely factored into her communication plan
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1二级建造师法规知识点:外商投资建筑业企业的规定
- 2沪昆客专王家坞特大桥架设完毕
- 32015年咨询工程师《工程项目组织与管理》每日一练(10.21)
- 42015年咨询工程师《咨询概论》模拟题(16)
- 5工业增加值创八月新高 多项指标企稳上升 经济回暖料延续
- 62015造价员考试工程价款结算知识:工程预付款结算
- 7燃气管道施工组织设计11P
- 82015年咨询工程师《分析与评价》每日一练(7.2)
- 92015年咨询工程师《项目组织与管理》模拟题(14)
- 10某道路工程雨污水管道施工方案11P
- 11某医院病房楼建筑防水工程施工方案
- 12一级建造师管理与实务复习要点:价款调整
- 13复合盾构施工系列工法34页(掘进 始发 过站 到站)
- 14有什么工具可以有效较少项目管理的漏洞?
- 15如何预防搅拌车轮毂甩油轮毂轴承
- 162015年四平造价工程师考试用书
- 17咨询工程师《工程咨询概论》模拟练习题(2)
- 182015年招标师《专业实务》辅导:货物评标的详细评审要点
- 192015年伊克昭盟造价工程师考试用书
- 202015年咨询工程师《咨询概论》每日一练(2.26)
- 21PMP认证考试最新练习题及参考答案(21-27套)
- 22造价工程师复习资料:综合税率的计算因企业所在地的不同而不同
- 23现代咨询方法与实务知识点:成本与费用估算要求
- 24安全工程师生产法复习资料——开展调查研究
- 25注册咨询工程师《工程咨询概论》预测模拟试题(10)
- 26安全工程师辅导资料:电器倒闸操作确保人身设备安全3
- 27评标委员会如何评审投标文件
- 28[辽宁省]大连市05造价工程师5月10—30日报考
- 29一级建造师管理与实务复习要点:灌注混凝土
- 30[湖南]新航站楼工程施工施工平面布置图(地下室 主体 装饰)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼