成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼
PMP认证考试练习题及参考答案(一)
1. communications is best described as:
a. an exchange of information.
b. providing written or oral directions.
c. consists of senders and receivers
d. effective listening.
e. all of the above考试大论坛
ans: e
2. fixed price contracts place more risk on the:
a. owner
b. buyer
c. seller
d. contractor
e. c or d
ans: e考试大(www.Examda。com)
3. life cycle costing is the total cost to the customer for the acquisition and ownership over its full life. life cycle costing categories include the cost
of _____, _____, and _____.
a. r & d, maintainability, operation and support.
b. r & d, production, operation and support.来源:考试大
c. acquisition, operations, maintenance.
d. production, operations, maintenance.
e. none of the above
ans: b
4. management by objectives assumes that the team:
a. is receptive to an unstructured environment.
b. does not require close supervision.
c. possesses a self directed philosophy
d. identifies with project objectives.来源:考试大
e. all of the above.
ans: e

5. quality may be defined as:
a. conformance to requirements.
b. fitness for use.
c. continuous improvement of products and services
d. appeal to the customer
e. all of the above except b来源:考试大
ans: e
6. since risk is associated with most projects, the best course of action is to:
a. cover all project risks by buying appropriate insurance
b. ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.
c. avoid projects with clear and present risks
d. eliminate all known risks prior to the execution phase of the project
e. identify various risks and implement actions to mitigate their potential impact
ans: e
7. the process of choosing/documenting the best approach to achieve the project objectives is part of:
a. the scope baseline.
b. scope authorization来源:考试大网
c. scope definition
d. scope planning.
e. all of the above.
ans: d
8. time management is the allocation of time in a project's life cycle through the process of:
a. planning
b. estimating.
c. scheduling.
d. controlling
e. all of the above.
ans: e
9. a comprehensive definition of scope management would be:
a. managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
b. approval of the scope baseline.http://ks.examda.com
c. approval of the detailed project charter.
d. configuration control.
e. approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
ans: a
10. cost plus percentage of cost contracts are more desirable for the:
a. owner
b. buyer
c. seller
d. contractor
e. c or d
ans: e
11. management styles associated with production environments, such as assembly lines commonly include:
a. a directing style of leadership.
b. a lack of confidence in their workerswww.Examda.CoM
c. assumption that workers lack ambition and dislike responsibility
d. a theory x style of leadership
e. all of the above.
ans: e
12. quality management:
a. is another name for careful inspections.
b. is inversely related to productivity.
c. is primarily the responsiblity of management.
d. is primarily the responsibility of the workers.
e. is essentially a motivational technique.
ans: c