监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 签约案例 | 购买价格 | 在线试用 | 手机APP | 产品资料
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

PMP认证考试练习题及参考答案(二)

申请免费试用、咨询电话:400-8352-114

来源:考试大网1. the highest degrees of project risk and uncertainty are associated with the following phase of the project:
a. conceptual
b. execution
c. cut-over来源:www.examda.com
d. post project evaluation
e. a and d only
ans: a

2. the most common types of schedules are gantt charts, milestone charts, line of balance, and:
a. networks.
b. time phased events.
c. calendar integrated activities.
d. a and c only.
e. b and c only.
ans: a

3. which of the following is often overlooked in achieving effective communication?
a. speaking clearly
b. listening
c. interpreting
d. maintaining eye contact
e. manipulating the conversation
ans: b

4. which type of contract requires that the buyer keep the tightest labor/material cost control?
a. cost plus incentive fee
b. cost plus percentage of costs
c. cost plus fixed fee考试大论坛
d. firm fixed price
e. firm fixed price plus incentive
ans: b

5. a task-oriented family tree of activities is a:
a. detailed plan.
b. linear responsibility chart.
c. work breakdown structure.
d. cost account coding system.
e. work package description.
ans: c

6. adding 5 people to a 4 person team increases the communication channels by a factor of:
a. 2 times
b. 3 times
c. 4 times来源:考
d. 5 times
e. 6 times
ans: e

7. cost management includes:
a. cost estimating/forecasting.
b. cost budgeting/cost control.
c. cost applications.
d. all of the above.
e. a and b only.
ans: d

8. participative management:
a. involves the solicitation of information from all team members.
b. assumes that members avoid work and responsibility.
c. suggests the sharing of power and decision making.
d. employs a theory x style of leadership.
e. a and c
ans: e

9. the auditing function that provides feedback about the quality of output is referred to as:
a. quality control.
b. quality planning.
c. quality assurance.
d. quality improvement
e. all of the above.
ans: c

10. the lowest dollar amount 'at stake' is associated with the following phase of the project:
a. conceptual
b. execution来源:www.examda.com
c. cut-over
d. post project evaluation
e. a and d only
ans: a

11. the major disadvantage of a bar chart is:
a. lack of time-phasing.
b. cannot be related to calendar dates.
c. does not show activity interrelationships.
d. cannot be related to manpower planning.
e. cannot be related to cost estimates.
ans: c

12. which contract type consists of - target costs & profit, ceiling prices and shared ratio of risk?
a. cost plus incentive fee
b. cost plus percentage of costs
c. cost plus fixed fee
d. firm fixed pricewww.Examda.CoM
e. firm fixed price plus incentive
ans: e

发布:2007-03-02 10:51    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件