来源:考试大网1. the highest degrees of project risk and uncertainty are associated with the following phase of the project:
a. conceptual
b. execution
c. cut-over来源:www.examda.com
d. post project evaluation
e. a and d only
ans: a
2. the most common types of schedules are gantt charts, milestone charts, line of balance, and:
a. networks.
b. time phased events.
c. calendar integrated activities.
d. a and c only.
e. b and c only.
ans: a
3. which of the following is often overlooked in achieving effective communication?
a. speaking clearly
b. listening
c. interpreting
d. maintaining eye contact
e. manipulating the conversation
ans: b
4. which type of contract requires that the buyer keep the tightest labor/material cost control?
a. cost plus incentive fee
b. cost plus percentage of costs
c. cost plus fixed fee考试大论坛
d. firm fixed price
e. firm fixed price plus incentive
ans: b
5. a task-oriented family tree of activities is a:
a. detailed plan.
b. linear responsibility chart.
c. work breakdown structure.
d. cost account coding system.
e. work package description.
ans: c
6. adding 5 people to a 4 person team increases the communication channels by a factor of:
a. 2 times
b. 3 times
c. 4 times来源:考试大
d. 5 times
e. 6 times
ans: e
7. cost management includes:
a. cost estimating/forecasting.
b. cost budgeting/cost control.
c. cost applications.
d. all of the above.
e. a and b only.
ans: d
8. participative management:
a. involves the solicitation of information from all team members.
b. assumes that members avoid work and responsibility.
c. suggests the sharing of power and decision making.
d. employs a theory x style of leadership.
e. a and c
ans: e
9. the auditing function that provides feedback about the quality of output is referred to as:
a. quality control.
b. quality planning.
c. quality assurance.
d. quality improvement
e. all of the above.
ans: c
10. the lowest dollar amount 'at stake' is associated with the following phase of the project:
a. conceptual
b. execution来源:www.examda.com
c. cut-over
d. post project evaluation
e. a and d only
ans: a
11. the major disadvantage of a bar chart is:
a. lack of time-phasing.
b. cannot be related to calendar dates.
c. does not show activity interrelationships.
d. cannot be related to manpower planning.
e. cannot be related to cost estimates.
ans: c
12. which contract type consists of - target costs & profit, ceiling prices and shared ratio of risk?
a. cost plus incentive fee
b. cost plus percentage of costs
c. cost plus fixed fee
d. firm fixed pricewww.Examda.CoM
e. firm fixed price plus incentive
ans: e
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1项目管理与招标采购第五章:工作分解结构
- 2“中国首善”陈光标50亿家产或从汶川地震获利20亿
- 3招标师考试真题还可以用吗
- 4绵遂高速公路小间距隧道(实施)施工组织设计
- 52015年一级建造师《项目管理》精华知识点(16)
- 6招标师考试:最低价中标的危害
- 7沪昆高铁贵州段成功架设首孔900吨箱梁
- 8桐乡市2015年安全工程师考试报名时间确定:4月8日至22日
- 9某分离式钢筋混凝土箱涵施工
- 10贵州住房和城乡建设厅:二级建造师考试特别提示
- 11休闲广场景观工程施工组织设计
- 122015年造价员基础知识:建筑工程安全管理
- 13某大型铁路框架桥顶进施工
- 142015年招标师《法律法规》:科技项目招标
- 15【经验之谈】二建考试在即 考前培训有必要参加吗?
- 1613种农村垃圾处理模式有望在广西推广
- 172015年凯里市造价工程师报名入口
- 18某大桥主桥悬浇混凝土施工方法
- 192015年咨询工程师《工程项目组织与管理》每日一练(3.10)
- 20新建铁路武汉至广州客运专线重点隧道施工总承包某标段施工组织设计
- 21建设工程目标控制的措施典型题解(四)
- 22棚洞施工方法
- 23某桥预应力盖梁施工方法
- 24生产区车间工程施工组织设计120p
- 25PMP项目管理:项目成本管理练习题4
- 262015年咨询工程师考试《咨询概论》预测试题(5)
- 27造价工程师考试辅导资料:单价所包含内容
- 28秦皇岛2015年度注册安全工程师考试报名时间为4月22日至5月13日
- 292015年造价员基础知识:工程造价含义
- 302015年咨询工程师《工程项目组织与管理》每日一练(12.22)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼