1. Which of the following techniques can be used to integrate and measure a project’s schedule and cost performance?
Earned value management
Monte Carlo Process
Quality Management Plan
Utilize a matrix structure

要整合和衡量项目进度和成本绩效,能用下列哪项技术方法:
挣值管理
蒙托卡罗方法
质量管理计划
利用矩阵结构

2. A fully integrated project plan assists the project manager by:
Providing a complete reference for all organizational policies.
Providing the project manager with total project authority
Preventing input from the project sponsor.
Facilitating communications among project stakeholders.

完全整合的项目计划对项目经理的帮助是通过:
对所有的组织政策提供完全的参考
给项目经理全面职权
保护项目业主的投入
方便项目相关者之间的沟通

3. The true status of a project cannot be determined unless which of the following are jointly considered:
Project schedule and cost analysis
Project schedule and employee responsibilities
Scope baseline and management plan
Cost analysis and deliverables

要知道项目真实状态,必须结合考虑下列哪一项:
项目进度和成本分析
项目进度和员工责任
范围基准和管理计划
成本分析和工作成果

4. Which of the following is not used for reporting performance?
Bar charts
S-curves
Histograms
Fishbone diagrams

下列哪一种技术没有被用来报告绩效:
柱线图
S曲线
矩形图
鱼刺图

5. Communication technology factors that may affect the project include all but which one of the following?
A specific type of project instruction
The immediacy of the need for information
The availability of technology
The expected project staffing

可能影响项目的沟通技术因素包括所有下列事项,除了:
a. 专门类型的项目说明书
b. 信息需要的迫切性
c. 技术的可用性
d. 项目期望的人员配置

6. The project manager issued a series of status reports over the course of several months to address issues that had emerged in project negotiations with the contractor. This represents what form of communication?
Formal verbal communication
Formal written communication
Informal verbal communication
Informal written communication

项目经理发出了关于数月来项目状态一系列报告,用以表明在与合同方的项目谈判中出现的问题,这表示的是什么形式的沟通:
正式的言语沟通
正式的书面沟通
非正式的言语沟通
正式的书面沟通

7. Project management software:
Cannot be used as a communication tool
Is not considered a class of computer applications
Can assist with both planning and controlling project costs and schedules
Guarantees on time project completion

项目管理软件
不能用作沟通工具
没有被考虑为高级的计算机应用
能用来帮助规划和控制项目成本和进度
保证项目按时完成

发布:2007-03-02 10:48    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件