PMP认证考试练习题(二十三)(中英文)
1. Major difficulties arise when multiple projects need to managed in the functional organizational structure because of-
A. The level of authority of the project manager
B. Conflicts over the relative priorities of different projects in competition for limited resources
C. Project team members who are focused on their functional specialty rather than on the project
D. The need for the project manager to use interpersonal skills to resolve conflicts informally
1. 当多个项目需要在职能组织结构中进行管理的时候,会出现很大的困难,因为:
A. 项目经理的权限有限
B. 不同的项目在竞争有限资源过程中会发生冲突
C. 项目小组成员更关注职能部门的本职工作而不是与项目有关的工作
D. 需要项目经理运用个人交际能力非正式地解决冲突
2. The team you have organized for your new project consists of three people who will work full-time and five people who will support the project on a part-time basis. All team members know one another and have worked together in the past. To ensure a successful project start-up, your first step should be to
A. Meet with each team member individually to discuss assignments
B. Prepare a responsibility assignment matrix and distribute it to each team member
C. Distribute the project plan and WBS to the team
D. Hold a project kickoff meeting
2. 你为新项目组建的项目小组包括三个全职人员和五个兼职人员,所有小组人员相互认识并在过去一起共事。为了项目启动顺利,你的第一步是:
A.同每个小组成员单独会面,讨论任务分配
B.准备一个责任分配矩阵并分发给每个成员
C.将项目计划和工作分解结构分发给小组成员
D.举行项目动员大会
3. One organizational option for improving communications and teamwork is using a fight matrix. This approach also serves to facilitate-
A. Fast-tracking
B. Concurrent engineering
C. Resource leveling
D. Work on geographically dispersed or virtual teams
3. 一个公司为改善沟通和团队协作可以选择使用一个紧缩矩阵的形式把大家组织起来。这种方法还能促进
A. 快速赶工
B. 协作工程
C. 资源平衡
D. 地理上分散或虚拟团队的工作
4. Of the following types of historical information that can be used in risk identification, which is the least reliable?
A. Project files
B. Commercial databases
C. Project team knowledge
D. Lessons learned databases
4. 在以下可用于风险识别的历史信息中,最不可靠的是:
A. 项目的档案
B. 商业数据库
C. 项目小组知识
D. 经验数据库
5. The DeIphi technique is a particularly useful method for identifying risk to
A. Present a sequence of decision choices graphically to decision makers
B. Define the probability of occurrence of specific variables
C. Reduce bias in the analysis and keep any one person from haying undue influence on the outcome
D. Help take into account the attitude of the decision maker toward risk
5.德尔菲技术是特别有用的风险识别方法,目的是:
A. 为决策者提供图表式的一系列决策选择
B. 明确特定变量出现的概率
C. 减少分析过程中的偏见,防止任何人对分析结果施加不正当的影响
D. 有助于将决策者对风险的态度考虑进去
6. A workaround is-
A. An unplanned response to a negative risk event
B. A plan of action to follow when something unexpected occurs
C. A specific response to certain types of risk as described in the risk management plan
D. A proactive, planned method of responding to risks
6. 权变措施是指
A. 对负面风险事件的一个应急反应
B. 当没有预料到事情发生时遵循的一个行动计划
C. 对风险管理计划中描述的风险的具体回应
D. 一个前瞻性的、有计划的风险应对措施
7. Which term describes the failure by either the buyer or seller to perform part or all of the duties of a contract?
A. Termination of contract
B. Partial performance
C. Breach of contract
D. Contract waiver
7. 卖方或者买方部分或者全部没有履行合同义务属于
A. 合同终止
B. 部分履行
C. 违反合同
D. 合同弃权
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1煤矿井下预防冒顶的措施
- 2环氧树脂胶安全施工方法
- 32015年二级建造师《施工》重点:施工成本计划的类型
- 42015年咨询工程师《工程项目组织与管理》每日一练(6.21)
- 5室外给水管道施工工艺 14P
- 6工程质量事故调查组的职责包括哪些
- 72015年咨询工程师《宏观经济政策与发展规划》每日一练4.9
- 8巴西欲将世界杯球场改成住宅区 保留比赛功用
- 9FC板吊顶施工质量控制要点表
- 10安全工程师考试《安全生产管理》知识要点:安全控制论原理
- 11[济南]客运专线双线隧道施工组织设计(台阶法 双侧壁导坑法)
- 12中铁一局四公司雀儿山隧道主洞突破2000米大关
- 13安全工程师安全生产法复习资料——护理费
- 142015年安全工程师考试《安全生产技术》:烟花爆竹
- 152015年造价工程师考试辅导资料:阀门(1)
- 162015年咨询工程师《宏观经济政策》练习题(31)
- 17青海省人事考试中心公布2015年注册安全工程师考试网上报名安排
- 182015年二级建造师备考三招记忆法
- 192015年七台河造价工程师现场审核地点及时间
- 20项目管理中的圣吉学习型组织建设
- 21张家界2015年注册安全工程师考试报名审核时间为5月10日至12日
- 22GPS实时动态测量的虚拟建站方法及其应用
- 23合肥市为农民工工资添凭据 发布工程劳务分包指导价
- 242015咨询工程师现代咨询方法与实务案例分析(六)
- 25宿舍楼水电安装工程施工组织设计
- 26招标师职业水平考试:项目管理与招标采购第五章练习题2
- 272015年咨询工程师《政策与规划》每日一练(3.7)
- 28企业投资项目管理解决方案第四章
- 29山东省2015年造价工程师考试报名即将开始
- 30锚杆挡土墙施工工艺
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼