PMP认证考试试题精选(2)
A. Internal, formal, and horizontal
B. External, informal, and vertical
C. Oral, internal, and informal
D. Oral, external, and formal
32. Manual filing systems, electronic text databases, and project management soflware that allow team members to share information about the project are exanples of
A. A communication management plan
B. An information retrieval system
C. An information distribution system
D. A project management information system
33. During project team formation and during the early phases of a project, the most common
ource of conflict within the project teamis likely to be:
A. Schedules
B. Priorities
C. Technical opinions
D. Cost
34. During execution of a project, the most common source of conflict within the project team is likely to be:
A. Schedules
B. Priorities
C. Technical opinions
D. Cost
35.Of the following, which conThct resolution strategy is likely to yield the most productive results?
A. Withdrawing
B. Forcing
C. Compromising
D. Collaborating